PROJECT NAME : 50 Beded Ayurvedic Hospital Bhadrashi Varanasi |
Project Detail / Brief Description:
Ayurvedic medicines are known to offer several health benefits. |
Project Department: U.P. State Construction & Infrastructure Development Corporation Ltd. |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
Aniruddhu Prasad | varanasi.upsknn@rediffmail.com | 9454455973 |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 30/Nov/2018 | Project Planned Completion Date: 28/Feb/2021 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
Internal Electrification Work | 01/01/2021 | 15/01/2021 | 100% |
First Floor Flooring Work | 16/03/2021 | 31/03/2021 | 100% |
Sanitory Work | 16/03/2021 | 31/03/2021 | 90% |
Ground Floor Work | 16/03/2021 | 31/03/2021 | 80% |
Sub Structure Work | 01/01/2021 | 15/01/2021 | 100% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Land equalization & Labeling | Land equalization & Labeling Work Complete Hand over Dated 23.12.2021 | 30/11/2018 | 30/09/2019 | - | 100% |
2 | Sub Structure Works | Sub Structure Works complete Hand over Dated 23.12.2021 | 30/11/2019 | 15/02/2021 | - | 100% |
3 | Balance Slab Casting of Second Floor | Work Complete Hand over Dated 23.12.2021 | 16/06/2020 | 25/06/2020 | - | 100% |
4 | Ground Floor - Floor Work | Ground Floor - Floor Work Complete Hand over Dated 23.12.2021 | 16/06/2020 | 15/02/2021 | - | 100% |
5 | Sanitory Work | Sanitory Work Complete Hand over Dated 23.12.2021 | 16/06/2020 | 15/02/2021 | - | 100% |
6 | First Floor - Flooring Work | First Floor - Flooring Work Complete Hand over Dated 23.12.2021 | 20/09/2020 | 15/02/2021 | - | 100% |
7 | Internal Electrification Work | Internal Electrification Complete Hand over Dated 23.12.2021 | 16/09/2020 | 15/02/2021 | - | 100% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
641 Lac. | 0 Lac. | 608 Lac. | 576 Lac. | 65 Lac. |