PROJECT NAME :  Construction of 200 Girls Hostel for Research Scholars at BHU Varanasi
Project Detail / Brief Description:

Construction of 200 Girls Hostel for Research scholars at BHU Varanasi.


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

Provide accommodation for girl students


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 27/Feb/2020 Project Planned Completion Date: 31/Jul/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
25%Road work 01/08/2021 15/08/2021 5%
Internal plaster of 8th floor. Tile work 6th floo 16/03/2021 31/03/2021 100%
Internal plaster of 6th floor. Tile work 5th floo 01/03/2021 15/03/2021 100%
External plaster back face of the building. Inter 01/03/2021 15/03/2021 100%
Completion of columns for Overhead Water Tank, Mum 01/01/2021 15/01/2021 100%
Completion of concreting for terrace slab. Brick 01/01/2021 15/01/2021 100%
Completion of shuttering of terrace slab. Brick w 01/01/2021 15/01/2021 100%
Brick work of 5th floor. completion of Internal f 01/01/2021 15/01/2021 100%
Completion of 50% of 8th slab. Brick work of 4th 01/11/2020 15/11/2020 100%
Completion of 6th slab. Masonry work of 1st floor. 16/10/2020 31/10/2020 100%
Completion of 3rd slab. 01/10/2020 15/10/2020 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 1st Milestone
RCC of Foundation upto plinth level & other works upto plinth level including submission & approval of all shop drawings and associated E&M agencies. 27/02/2020 31/08/2020 - 100%
2 2nd Milestone
RCC slab upto floor level 4, brick work upto floor level 3 including associated E&M works 01/09/2020 31/10/2020 - 100%
3 3rd Milestone
RCC slab upto floor level 8, brick work upto floor level 6, Internal finishing works upto floor level 5 including associated E&M works. 01/11/2020 31/01/2021 - 100%
4 4th milestone
RCC slab upto floor level 10 (terrace level), Brick work upto floor level 8, Internal finishing works upto floor level 7 including associated E&M works. 01/02/2021 31/03/2021 - 0%
5 5th Milestone
(a) Completion of all RCC works, Brick works, plastering work and plumbing works
(b) Completion of all flooring works etc. complete in all respect
(c) Wall conduiting, fixing of switch, socket boxes and DBs of
all floors
(d) Installation of all major materials such as panels, lift, equipments, cables, CCTV, LAN Networking, etc. and any other materials as required.
01/04/2021 31/05/2021 - 0%
6 6th Milestone
(a) Completion of internal & external painting & false ceiling works
(b) Completion of external plumbing, sewerage work, drainage, road work, boundary & gate work, Horticulture works etc. complete.
(c) Installation of fan and fittings in all buildings complete.
(d) Testing and commissioning of lifts.
(e) Completion of DG set and submission for
Inspection by CEA.
01/06/2021 30/06/2021 - 0%
7 7th Milestone
Completion of all works in all respect including testing and Commissioning. 01/07/2021 31/08/2021 - 15%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
2878 Lac. 0 Lac. 1918 Lac. 1860 Lac. 1018 Lac.