PROJECT NAME :  Construction of 50 MLD STP at Ramana, Varanasi
Project Detail / Brief Description:

50 MLD STP - 01 No., Effluent Pipe line - 5-5 Km. and
Rehabilitation of MPS and Rising main.


Project Department:

Ganga Pollution Prevention Unit, U.P. Jal Nigam

Associated Yojna Name:

Namami Gange

Goals, Objectives and Benefits of Project:

Abatement of pollution in River Ganga by
interception of sewage flowing through three drains and discharge of the same after
treatment.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
S.K. Burman ganga@gmail.com 9450596859

 PROJECT DATES
Project Planned Start Date: 19/Feb/2018 Project Planned Completion Date: 31/Mar/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Construction of 50 MLD STP at Ramana
Construction of STP is completed and commissioned. 01/05/2020 31/03/2021 - 100%
2 Laying of treated effluent pipe line along with associated works
Completed. 01/05/2020 31/01/2021 - 100%
3 Rehabilitation of Associated Infrastructure
Completed 01/05/2020 31/01/2021 - 100%
4 Construction of Protection earthen Bund and Miscellaneous works
completed 01/05/2020 30/09/2021 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
16131 Lac. 0 Lac. 5924 Lac. 5924 Lac. 10207 Lac.