Back     

Project Details

PROJECT NAME :  Construction of Permanent Building of Inter University Center for Teacher Education (IUCTE) BHU Varanasi
Project Detail / Brief Description:

This campus is being constructed to impart training to Teachers upto University Level


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 11/Oct/2019 Project Planned Completion Date: 30/Sep/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
3rd floor room tile in residential block. 4th flo 01/08/2021 15/08/2021 25%
Completion of concreting of slab at Level 7 of Aca 16/03/2021 31/03/2021 100%
Completion of RCC for terrace slab of Auditorium 01/03/2021 15/03/2021 100%
Completion of staging and 50% shuttering for Lect 01/08/2021 15/08/2021 100%
Completion of tile work upto 7th floor of Guest Ho 01/01/2021 15/01/2021 100%
Completion of tile work upto 4th floor of Guest Ho 01/01/2021 15/01/2021 100%
Completion of tile work for 1st & 2nd floor of Gue 01/01/2021 15/01/2021 100%
Completion of 50% of 1st slab of Residential Bloc 16/11/2020 30/11/2020 100%
Completion of balance portion 50% 1st slab of Acad 01/11/2020 15/11/2020 100%
Completion of 50% 1st slab of Academic Block. Com 16/10/2020 31/10/2020 100%
Completion of Auditorium steps of Academic Block. 01/10/2020 15/10/2020 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 1st Milestone
Completion of RCC Foundation work 11/10/2019 31/05/2020 - 100%
2 2nd Milestone
RCC slab upto floor level 3 for Academic Block, upto floor level 4 for Residential Block & Guest House along with respective E&M work. 01/06/2020 30/11/2020 - 70%
3 3rd Milestone
RCC slab upto floor level 6 for Academic Block upto floor level 7 for Residential Block & Guest House along with respective E&M work 01/12/2020 31/12/2020 - 10%
4 4th milestone
Complete RCC work including OH water tank, lift room for Academic Block, Residential Block & Guest House along with respective E&M work 01/01/2021 31/03/2021 - 0%
5 5th Milestone
(i) Complete external plaster of all buildings.
(ii) Complete Flooring work of all building.
(iii) Fixing of doors, windows of all buildings.
(iv) Fixing of sanitary and plumbing fittings.
(v) Wiring complete in all buildings.
(vi) Installation & testing of switch, socket complete in all buildings.
(vii) Service connection to the building with cable and panel
Complete in all buildings.
(viii) Installation of outdoor lighting, pole and fittings, feeder pillar
etc.
01/04/2021 30/06/2021 - 0%
6 6th Milestone
(i) Completion of internal & external painting, false ceiling of
all buildings,
(ii) Completion of external plumbing, sewerage work, drainage
and road work.
(iii) Installation of fan and fittings in all buildings complete
(iv) Installation of air conditioning system in all respect.
(v) Testing and commissioning of lifts.
(vi) Completion of DG set & substation work
(vii) Completion of Fire Fighting and Fire Alarm Work.
01/07/2021 31/08/2021 - 10%
7 7th Milestone
Completion of all works in all respect including testing and commissioning 01/09/2021 30/09/2021 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
10736 Lac. 0 Lac. 6720 Lac. 6335 Lac. 4401 Lac.



Back