PROJECT NAME : Construction of Permanent Building of Inter University Center for Teacher Education (IUCTE) BHU Varanasi |
Project Detail / Brief Description:
This campus is being constructed to impart training to Teachers upto University Level |
Project Department: Central Public Works Department (CPWD) |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
ASHOK KUMAR GUPTA | eevpd@rediffmail.com | 9999798241 | Project Head |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 11/Oct/2019 | Project Planned Completion Date: 30/Sep/2021 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
3rd floor room tile in residential block. 4th flo | 01/08/2021 | 15/08/2021 | 25% |
Completion of concreting of slab at Level 7 of Aca | 16/03/2021 | 31/03/2021 | 100% |
Completion of RCC for terrace slab of Auditorium | 01/03/2021 | 15/03/2021 | 100% |
Completion of staging and 50% shuttering for Lect | 01/08/2021 | 15/08/2021 | 100% |
Completion of tile work upto 7th floor of Guest Ho | 01/01/2021 | 15/01/2021 | 100% |
Completion of tile work upto 4th floor of Guest Ho | 01/01/2021 | 15/01/2021 | 100% |
Completion of tile work for 1st & 2nd floor of Gue | 01/01/2021 | 15/01/2021 | 100% |
Completion of 50% of 1st slab of Residential Bloc | 16/11/2020 | 30/11/2020 | 100% |
Completion of balance portion 50% 1st slab of Acad | 01/11/2020 | 15/11/2020 | 100% |
Completion of 50% 1st slab of Academic Block. Com | 16/10/2020 | 31/10/2020 | 100% |
Completion of Auditorium steps of Academic Block. | 01/10/2020 | 15/10/2020 | 100% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | 1st Milestone | Completion of RCC Foundation work | 11/10/2019 | 31/05/2020 | - | 100% |
2 | 2nd Milestone | RCC slab upto floor level 3 for Academic Block, upto floor level 4 for Residential Block & Guest House along with respective E&M work. | 01/06/2020 | 30/11/2020 | - | 70% |
3 | 3rd Milestone | RCC slab upto floor level 6 for Academic Block upto floor level 7 for Residential Block & Guest House along with respective E&M work | 01/12/2020 | 31/12/2020 | - | 10% |
4 | 4th milestone | Complete RCC work including OH water tank, lift room for Academic Block, Residential Block & Guest House along with respective E&M work | 01/01/2021 | 31/03/2021 | - | 0% |
5 | 5th Milestone | (i) Complete external plaster of all buildings. (ii) Complete Flooring work of all building. (iii) Fixing of doors, windows of all buildings. (iv) Fixing of sanitary and plumbing fittings. (v) Wiring complete in all buildings. (vi) Installation & testing of switch, socket complete in all buildings. (vii) Service connection to the building with cable and panel Complete in all buildings. (viii) Installation of outdoor lighting, pole and fittings, feeder pillar etc. | 01/04/2021 | 30/06/2021 | - | 0% |
6 | 6th Milestone | (i) Completion of internal & external painting, false ceiling of all buildings, (ii) Completion of external plumbing, sewerage work, drainage and road work. (iii) Installation of fan and fittings in all buildings complete (iv) Installation of air conditioning system in all respect. (v) Testing and commissioning of lifts. (vi) Completion of DG set & substation work (vii) Completion of Fire Fighting and Fire Alarm Work. | 01/07/2021 | 31/08/2021 | - | 10% |
7 | 7th Milestone | Completion of all works in all respect including testing and commissioning | 01/09/2021 | 30/09/2021 | - | 0% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
10736 Lac. | 0 Lac. | 6720 Lac. | 6335 Lac. | 4401 Lac. |