PROJECT NAME : Development and Beautification of Pandeypur Pond |
Project Detail / Brief Description:
Project has been dropped as per the direction of VSCL Board on account of land ownership and court case issues. |
Project Department: Smart City Varanasi |
Associated Yojna Name: Smart City Mission |
||
Goals, Objectives and Benefits of Project:
1. Entrance Plaza with Ticketing Provision. |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
D.P. Mishra | deo.mishra@repl.global | 9990065441 | Infrastructure Specialist, PMC-VSCL |
Sunil Kumar | mail@varanasismartcity.gov.in |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 08/Jan/2020 | Project Planned Completion Date: 31/Dec/2021 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Cleaning of Ponds | due to stay of Honable court work is held | 15/02/2020 | 31/10/2020 | - | 45% |
2 | Dismantling and removing of encroachment /waste | due to stay of Honable court work is held | 15/07/2020 | 31/10/2020 | - | 10% |
3 | Boundary Wall and Drain Construction | Due to stay order of Honable court work is on hold. | 15/06/2020 | 30/10/2020 | - | 15% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
712 Lac. | 0 Lac. | 712 Lac. | 34 Lac. | 678 Lac. |