Project Details

PROJECT NAME :  Construction of Degree College (Sardar Vallabhbhai Patel) at Sevapuri Varanasi
Project Detail / Brief Description:

Construction of Degree College (Sardar Vallabhbhai Patel) at Sevapuri Varanasi


Project Department:

Uttar Pradesh Rajkiya Nirman Nigam Limited (UPRNNL) Varanasi

Associated Yojna Name:

Construction Degree Collage at Shivapuri Varanasi

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. B. Singh gmald.bhadohi@gmail.com 8400400488 Project Manager
UPRNN Varanasi Zone gmvns.bhadohi@gmail.com 8400400488

 PROJECT DATES
Project Planned Start Date: 01/Aug/2019 Project Planned Completion Date: 31/Dec/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
WORK COMPLETED 01/01/2021 15/01/2021 100%
प्लिन्थ बीम की ढला 01/01/2021 15/01/2021 24%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 MAIN BUILDING (G+3)
प्लिन्थ बीम की ढलाई, प्लिन्थ में मिट्टी भराई एवं सुपर स्ट्रक्चर में आर0सी0सी0 कालम का कार्य प्रगति पर। 01/08/2019 31/12/2021 - 24%
2 TUBE WELL, BORING & SUBMERSIBLE PUMP
पूर्ण। 01/08/2019 31/08/2020 - 100%
3 Boundary Wall & Gate
NOT STARTED 01/12/2020 31/12/2021 - 0%
4 INDIA MARKA-II HAND PUMP
NOT STARTED 01/12/2020 31/12/2021 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
760.35 Lac. 0 Lac. 430 Lac. 158 Lac. 602.35 Lac.