PROJECT NAME :  Construction of Varuna River Bridge Lahartara - Phoolwaria Marg Imaliyaghat in District Varanasi
Project Detail / Brief Description:

Varuna bridge on lahartara phulwaria J.P. mehta inter college via central jail via shivpur chungi marg


Project Department:

U.P. State Bridge Corporation Ltd. - Varanasi Unit

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Rohit Mishra bcuvaranasi@gmail.com 8765977741 Dy. Project Manager

 PROJECT DATES
Project Planned Start Date: 01/May/2018 Project Planned Completion Date: 31/Jan/2021

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 फ़ाउंडेशन
भूमि अध्याप्ति का कार्य लो0 नि0 वि0 द्र्वरा किया जा रहा है भूमि की मापी एव किसानो की सहमति प्राप्त कर रजिस्ट्री का कार्य अपेक्षित है 31/03/2019 31/03/2020 - 35%
2 सब स्टृक्चर
कार्य प्रगति पर है 30/04/2019 30/04/2020 - 10%
3 सुपर स्ट्रक्चर
कार्य प्रगति पर है 31/12/2019 30/06/2020 - 0%
4 पहुँच मार्ग
भूमि अध्यापति के उपरांत कार्य प्रारम्भ किया जाना है 29/02/2020 31/12/2020 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
3464.85 Lac. 0 Lac. 2969.66 Lac. 495.19 Lac.