Project Details

PROJECT NAME :  Construction of Two Wheeler Multi Level Parking at Godowalia Varanasi
Project Detail / Brief Description:

Two Wheeler Parking for 375 Two Wheelers


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

Parking for Two Wheeler


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 22/Apr/2019 Project Planned Completion Date: 31/Mar/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
facade work, lift work, GF development 16/02/2021 28/02/2021 0%
facade work, lift work, GF development 01/02/2021 15/02/2021 40%
Deck sheeting and casting of slabs 01/02/2021 15/02/2021 100%
Mumty room structure to be completed. 01/02/2021 15/02/2021 100%
Machine room structure to be completed 01/02/2021 15/02/2021 100%
1 staircase balance to be completed. 01/02/2021 15/02/2021 100%
Erection of structure work completed 01/01/2021 15/01/2021 100%
Erection 60% to be completed. Target achieved 16/10/2020 31/10/2020 100%
Erection target achieved. 01/10/2020 15/10/2020 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 2nd Milestone
Target :
Erection of complete superstructure including deck slabs.
Achievements:
completed
01/08/2020 31/10/2020 - 100%
2 3rd Milestone
Installation of one lift balance. All other works completed. 01/11/2020 30/06/2021 - 95%
3 1st milestone
Foundation work completed 06/02/2020 31/07/2020 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1955 Lac. 0 Lac. 1764 Lac. 1250 Lac. 705 Lac.