PROJECT NAME :  Construction of Two Wheeler Multi Level Parking at Godowalia Varanasi
Project Detail / Brief Description:

Two Wheeler Parking for 323 Two Wheelers


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

Parking for Two Wheeler


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 22/Apr/2019 Project Planned Completion Date: 31/Dec/2020

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 2nd Milestone
Target :
Erection of complete superstructure including deck slabs.
Achievements:
Erection work of 29 columns out of 33 is completed. Deck sheet material is received. Installation will start shortly.
01/08/2020 31/10/2020 - 60%
2 3rd Milestone
Target:
Complete structure work including facade and external development
Internal electrical work, fire fighting (50%), fire alarm (50%), procurement of lift material
01/11/2020 31/12/2020 - 1%
3 1st milestone
Foundation work completed 06/02/2020 31/07/2020 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1955 Lac. 0 Lac. 1000 Lac. 829 Lac. 1126 Lac.