PROJECT NAME : Construction of Two Wheeler Multi Level Parking at Godowalia Varanasi |
Project Detail / Brief Description:
Two Wheeler Parking for 375 Two Wheelers |
Project Department: Central Public Works Department (CPWD) |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project:
Parking for Two Wheeler |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
ASHOK KUMAR GUPTA | eevpd@rediffmail.com | 9999798241 | Project Head |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 22/Apr/2019 | Project Planned Completion Date: 31/Dec/2020 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
Deck sheeting and casting for 2 nos. slabs out of | 01/01/2021 | 15/01/2021 | 30% |
Mumty room structure to be completed. | 01/01/2021 | 15/01/2021 | 20% |
Machine room structure to be completed | 01/01/2021 | 15/01/2021 | 45% |
1 staircase balance to be completed. | 01/01/2021 | 15/01/2021 | 80% |
Erection of structure work completed | 01/01/2021 | 15/01/2021 | 100% |
Erection 60% to be completed. Target achieved | 16/10/2020 | 31/10/2020 | 100% |
Erection target achieved. | 01/10/2020 | 15/10/2020 | 100% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | 2nd Milestone | Target : Erection of complete superstructure including deck slabs. Achievements: Erection work of 29 columns out of 33 is completed. Deck sheet material is received. Installation will start shortly. | 01/08/2020 | 31/10/2020 | - | 100% |
2 | 3rd Milestone | Target: Complete structure work including facade and external development Internal electrical work, fire fighting (50%), fire alarm (50%), procurement of lift material | 01/11/2020 | 31/12/2020 | - | 75% |
3 | 1st milestone | Foundation work completed | 06/02/2020 | 31/07/2020 | - | 100% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
1955 Lac. | 0 Lac. | 1000 Lac. | 1020 Lac. | 935 Lac. |