PROJECT NAME :  Construction of Fire Station Pindra Varanasi
Project Detail / Brief Description:

Boundary wall Complete. Main Building of FF slab casted.


Project Department:

U.P. Awas Vikas- Construction Unit

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
RAJESH RANJAN upavppm@gmail.com 8795811690

 PROJECT DATES
Project Planned Start Date: 07/Feb/2020 Project Planned Completion Date: 31/Dec/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
BRICK WORK UPTO PLINTH LEVEL 16/02/2021 28/02/2021 100%
MAIN BUILDING BRICK WORK COMPLETE 16/02/2021 28/02/2021 100%
Brick work in progress. 01/01/2021 15/01/2021 30%
Brick work in Progress. 01/12/2020 15/12/2020 10%
Main Building FF slab complete. 16/11/2020 30/11/2020 100%
Ground Floor slab casting 01/10/2020 15/10/2020 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Boundary Wall work
work in progress 01/07/2020 15/08/2020 - 40%
2 main building gGF SLAB
FOUNDATION WORK IN PROGRESS 01/07/2020 31/08/2020 - 10%
3 MAIN BUILDING FF SLAB
SLAB COMPLETED 09/07/2020 18/11/2020 - 100%
4 MAIN BUILDING FINISHING WORK
BRICK WORK IN PROGRESS 18/11/2020 31/03/2021 - 10%
5 TYPE A FOUNDATION WORK
TYPE A FOUNDATION WORK 25/01/2021 28/02/2021 - 30%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
708.72 Lac. 0 Lac. 177 Lac. 177 Lac. 531.72 Lac.