PROJECT NAME :  Construction of Underground Parking at Circut House Campus Kachahri Varanasi
Project Detail / Brief Description:

70% first level and 2nd level roof laid. remaining raft foundation work in progress. Revised estimate Rs. 2682.95 Lakh sent to urban and housing planning department.


Project Department:

U.P. Awas Vikas- Construction Unit

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Samar Upadhayay upavppm@gmail.com 8795810183

 PROJECT DATES
Project Planned Start Date: 06/Mar/2019 Project Planned Completion Date: 31/Mar/2021

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Part-2 Raft foundation work.
Work in Progress. 26/06/2020 05/07/2020 - 70%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1915.81 Lac. 0 Lac. 1532.64 Lac. 1532.64 Lac. 383.17 Lac.