PROJECT NAME :  Channelization & Shore Development of Varuna River
Project Detail / Brief Description:

Channelization & Shore Development of Varuna River completed. Crossing of sewer pipe line under railway line to joint the sump to SPS Chaukaghat through trenchless pipe work in progress. 60Mtr casing work completed.


Project Department:

Uttar Pradesh Project Corporation Limited

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Raj Nath Yadav pm3@upprojects.org 9839511599
Raj Nath Yadav pm_3@upprojects.org 9454419141

 PROJECT DATES
Project Planned Start Date: 20/Jul/2016 Project Planned Completion Date: 31/Dec/2020

15 Days Task
 Task Name Start Date End Date Percentage(%)
Channelization work completed. Connecting Sump to 01/12/2020 15/12/2020 10%
Channelization work completed. 98 Mtr. casing pipe 16/11/2020 30/11/2020 15%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Sump to S.P.S. Chaukaghat by trenchless method work
Crossing of sewer pipe line under railway line to joint the sump to SPS Chaukaghat through trenchless pipe is under progress. 60 Mtr. cashing pipe work completed. Due to rainy season the Railway Deptt. given the instruction to stop the work in respect of security purpose. 01/06/2020 15/07/2020 - 35%
2 Sump to S.P.S. Chaukaghat by trenchless method work
Crossing of Sewer pipe line through trenchless method is in progress. Laying of 98 Mtr. casing pipe & 108Mtr. carrier pipe work completed. 20/07/2016 31/12/2020 - 70%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
19544.27 Lac. 0 Lac. 19036.2 Lac. 19036.2 Lac. 508.07 Lac.