PROJECT NAME :  Bridge Over River Varuna on Koniya - Salarpur Marg at Koniya Ghat in District Varanasi
Project Detail / Brief Description:

Varuna Bridge on Koniya Ghat on Koniya - Salarpur Marg


Project Department:

U.P. State Bridge Corporation Ltd. - Varanasi Unit

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Rohit Mishra bcuvaranasi@gmail.com 8765977741 Dy. Project Manager

 PROJECT DATES
Project Planned Start Date: 01/May/2018 Project Planned Completion Date: 28/Feb/2021

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 फ़ाउंडेशन
नीव का कार्य पूर्ण 01/05/2018 31/08/2019 - 35%
2 सब स्टृक्चर
सब स्टृक्चर का कार्य प्रगति पर है 01/02/2019 31/12/2019 - 20%
3 सुपर स्ट्रक्चर
सुपर स्ट्रक्चर कार्य प्रगति पर है 01/09/2019 31/03/2020 - 5%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
2621.15 Lac. 0 Lac. 1250.34 Lac. 1370.81 Lac.