PROJECT NAME :  Bridge Over River Varuna on Babatpur- Kapsethi- Bhadoi Marg Km. 14 at (kalikadham) in Distt Varanasi
Project Detail / Brief Description:

Constrution of Bridge River Varuna at kalikadham on babatpur- kapsethi- Bhadoi Road


Project Department:

U.P. State Bridge Corporation Ltd. - Varanasi Unit

Associated Yojna Name:

Rajya Yojana

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Rohit Mishra bcuvaranasi@gmail.com 8765977741 Dy. Project Manager

 PROJECT DATES
Project Planned Start Date: 01/May/2020 Project Planned Completion Date: 30/Jun/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
स्थानीय काश्तकारो 01/12/2020 15/12/2020 5%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 फ़ाउंडेशन
कार्य प्रगति पर है 01/06/2020 30/03/2021 - 5%
2 सब स्टृक्चर
माह 10/20 मे कार्य प्रारम्भ कराया जाना प्रस्तावित है 01/10/2020 30/04/2021 - 0%
3 सुपर स्ट्रक्चर
माह 11/20 मे कार्य प्रारम्भ कराया जाना प्रस्तावित है 01/11/2020 30/06/2021 - 0%
4 पहुँच मार्ग
माह 11/20 मे कार्य प्रारम्भ कराया जाना प्रस्तावित है 01/11/2020 30/06/2021 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1913.8 Lac. 0 Lac. 1531.04 Lac. 97.96 Lac. 1815.84 Lac.