PROJECT NAME :  Regional Institute of Opthalmology (G+5) IMS BHU Varanasi
Project Detail / Brief Description:

Structure for Regional Institute of ophthalmology (G+5) building at IMS, BHU, Varanasi.


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 13/May/2019 Project Planned Completion Date: 31/Dec/2020

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Sixth Millstone Completion of finishing activities and External Development Works including testing and commissioning of E & M services.
Completion of whole work (Civil + Electrical) i/c installation, testing & commissioning of E&M equipments. 12/07/2020 12/12/2020 - 85%
2 First MileStone
Civil: Complete foundation work up to plinth level.
Electrical: Approval of associate agency for E&M work.
Submission and approval of shop drawings for all floor of E&M work.
13/05/2019 12/09/2019 - 100%
3 Second Milestone
Civil: Structure complete 3rd floor slab level.
Brick work completed at 2nd floor level.
Electrical: Laying of conduit and DBs of internal EI & fire fighting wherever brickwork is completed.
13/09/2019 12/01/2020 - 100%
4 Third Milestone
Civil: Structure complete 5th floor slab level.
Brick work completed at 4th floor level.
Electrical: Laying of conduit and DBs of internal EI & fire fighting wherever brickwork is completed.
13/01/2020 12/04/2020 - 100%
5 Fourth Milestone
Civil: Structure completed i/c mumty, machine room. Brick work & plaster completed. Flooring completed.
Electrical: Laying of conduit, switch boxes and DBs & wiring of EI & fire fighting wherever plaster is completed.
Supply of all E&M equipments at site.
13/04/2020 12/07/2020 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
2963 Lac. 0 Lac. 2610 Lac. 1965 Lac. 998 Lac.