PROJECT NAME :  Renovation and Upgradation of Sowa Rigpa Pharmacy at Sarnath Varanasi (CIHTS SARNATH)
Project Detail / Brief Description:

Renovation and upgradation of Sowa Rigpa Pharmacy at sarnath varanasi (CIHTS SARNATH)


Project Department:

Uttar Pradesh Rajkiya Nirman Nigam Limited (UPRNNL) Varanasi

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. B. Singh gmald.bhadohi@gmail.com 8400400488 Project Manager
UPRNN Varanasi Zone gmvns.bhadohi@gmail.com 8400400488

 PROJECT DATES
Project Planned Start Date: 31/Jan/2020 Project Planned Completion Date: 31/Dec/2020

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Renovation & Up-gradation of Sowa Rigpa Pharmacy At CIHTS Sarnath Varanasi
एम0एस0 शेड, प्लास्टर, ब्रिक वर्क का कार्य 100 प्रतिशत पूर्ण। फ्लोरिंग का कार्य 60 प्रतिशत कार्य पूर्ण, पेंटिंग का कार्य प्रगति पर। विद्युतीकरण का कार्य प्रगति पर 31/01/2020 30/09/2020 - 70%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
98.31 Lac. 0 Lac. 45.1 Lac. 53.21 Lac.