PROJECT NAME :  Redevelopment of Wards of Old Kashi-Jangambari Ward
Project Detail / Brief Description:

Improvise infrastructure such as water supply, sewerage system, artistic painting and efficient lighting of the ward for better environmental quality while preserving the local culture and heritage.


Project Department:

Smart City Varanasi

Associated Yojna Name:

Smart City Mission

Goals, Objectives and Benefits of Project:

1.Retrofitting of the Old Kashi Streets – Chunar Stone flooring,Strengthening of street service infrastructure
2.Replacement of Sewerage Line
3.Replacement of water supply line
4.Provision of Ducks for laying services in future.
5.Artisting painting work on property wall
6.Preserving the character of Old streets of Kashi.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
D.P. Mishra deo.mishra@repl.global 9990065441 Infrastructure Specialist, PMC-VSCL
Sunil Kumar mail@varanasismartcity.gov.in

 PROJECT DATES
Project Planned Start Date: 28/May/2020 Project Planned Completion Date: 31/Dec/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
Stone patiya removal work, Sewer pipeline work com 16/10/2020 31/10/2020 96%
Stone patiya removal work, Sewer pipeline- 100 mtr 16/10/2020 31/10/2020 60%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Mobilization of Manpower and T&P
Completed. 01/06/2020 30/06/2020 - 100%
2 Procurement of DI Pipes and Accessories
Work in progress. 06/06/2020 31/10/2020 - 90%
3 Procurement of RCC Pipes and Inter Connection
Work in progress. 11/06/2020 31/10/2020 - 90%
4 Procurement of Construction Material
Work in progress 11/06/2020 25/11/2020 - 70%
5 Work from 0 M to 250 M
Stone patiya removal work, Sewer pipeline, and water supply laying, Manhole construction work completed. 10/08/2020 20/09/2020 - 100%
6 Work from 251 to M 500 M
Stone patiya removal work 250 mtr Sewer pipeline work completed , and water supply laying 100% completed, Manhole construction work completed. 21/09/2020 31/01/2021 - 96%
7 Work from 501 M to 750 M
Stone patiya removal work, Sewer pipeline- 100 mtr completed and water supply laying, Manhole construction work in progress. 01/09/2020 10/11/2020 - 60%
8 Work from 751 M to 1000 M
choka stone-50%, sewar line-100%,water line-100%, PCC-75% 11/11/2020 31/01/2021 - 75%
9 Laying of PCC Work 250 mtr stretch
250 mtr completed 13/10/2020 30/11/2020 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1265 Lac. 0 Lac. 1265 Lac. 610 Lac. 655 Lac.