PROJECT NAME :  Redevelopment of Wards of Old Kashi-Raj Mandir
Project Detail / Brief Description:

1.Retrofitting of the Old Kashi Streets – Chunar Stone flooring,Strengthening of street service infrastructure 2.Replacement of Sewerage Line 3.Replacement of water supply line 4.Provision of Ducks for laying services in future. 5.Artisting painting work on property wall 6.Preserving the character of Old streets of Kashi


Project Department:

Smart City Varanasi

Associated Yojna Name:

Smart City Mission

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Rajesh Kumar Trivedi rajesh.trivedi@repl.global 8840994640 Construction Manager, PMC-VSCL
Sunil Kumar mail@varanasismartcity.gov.in

 PROJECT DATES
Project Planned Start Date: 26/Feb/2020 Project Planned Completion Date: 30/Sep/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
Work in progress. 16/10/2020 31/10/2020 25%
.Work in progress 16/10/2020 31/10/2020 70%
.Work in progress 16/10/2020 31/10/2020 90%
.Work in progress. 16/10/2020 31/10/2020 90%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Moblisation of Men power and T&P
completed 01/06/2020 30/06/2020 - 100%
2 Procurement of DI PIPE and Accessory
.Work in progress. 06/06/2020 31/10/2020 - 90%
3 Procurement of RCC PIPE and Interconnection
.Work in progress 06/06/2020 31/10/2020 - 90%
4 Procurement of Construction Material
.Work in progress 06/06/2020 25/11/2020 - 60%
5 Sewer pipe line and water supply line laying-200 mtr length
done 17/07/2020 31/08/2020 - 100%
6 Sewer pipe line and water supply line laying-200 mtr to 1000 mtr length
laying of sewer pipe line 1050 mtr and water supply line-500 mtr completed. 01/09/2020 20/10/2020 - 100%
7 Laying of PCC Work 500 mtr stretch
Laying of PCC 126 mtr completed. 10/10/2020 31/12/2020 - 25%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1353 Lac. 0 Lac. 1353 Lac. 856 Lac. 497 Lac.