PROJECT NAME :  4 laning of Varanasi Ring Road Phase I
Project Detail / Brief Description:

4 Lane of Varanasi Bypass from Km. 0.00 (Starting Point to Km. 271.300 of NH-2) to Km. 15.250 (End Point of KM. 11.170 of NH-29) including 4 laning of NH-29 from KM. 10+700 to Km. 12+000 (Total Project length 16.550 Km.)[Pkg I] in the state of U.P. under NHDP Phase IV on EPC mode.


Project Department:

National Highways Authority Of India (NHAI)

Associated Yojna Name:

NHDP-IV

Goals, Objectives and Benefits of Project:

It is a very important project for the development of Varanasi city and would relieve the Varanasi city from the congestion leading towards Lucknow, Gorakhpur, Azamgarh etc.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
S. B Singh var@nhai.org 9997870088 Project Director
K.C Verma var@nhai.org 9402477278 Manager (T)

 PROJECT DATES
Project Planned Start Date: 15/May/2015 Project Planned Completion Date: 30/Jun/2018

 METRICS
Key Metrics Current Planned
Total land under Acquisition 16.55 Km./89.27 Hact. 100% of land is physically available as on date Entire land acquisition is planned to be completed by 31st December 2017

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Milestone 1st
10% of contract value Rs. 261.09 Cr. i.e .

26.11 Cr. at 180th Days from project start date.

Milestone 1st: Achieved
05/05/2015 10/11/2014 - 10%
2 Milestone 2nd
35% of contract value Rs. 261.09 Cr. i.e.

91.38 Cr. at 365th days from project start date.

Milestone 2nd: Achieved
10/11/2015 31/07/2017 - 35%
3 Milestone 3rd
70% of contract value Rs. 261.09 Cr. i.e

182.76 Cr. at 620th days from project start date.


Actually 51.21% work achieved.
31/07/2017 12/04/2018 - 50%
4 Completion
100% of Contract value i.e.

Rs. 261.09 Cr. at end of 730th days.
12/04/2018 31/07/2018 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
26109 Lac. 0 Lac. 0 Lac. 9976 Lac. 16133 Lac.