PROJECT NAME :  Work of Rural electrification for System Strengthening & other work separation in Dist- Chandauli, Ghazipur, Jaunpur & Varanasi
Project Detail / Brief Description:

REC funded project for system strengthening of electricity distribution network by constructing new 33/11KV Sub station, Augmentation of SS, Feeder Separation, Interconnecting 33KV & new 33KV & 11KV Feeders. Project in divided in four Dist. Chandauli, Ghazipur, Jaunpur & Varanasi


Project Department:

Purvanchal Vidyut Vitaran Nigam Limited (PuVVNL)

Associated Yojna Name:

DEENDAYAL UPADHYAYA GRAM JYOTI YOJANA(DDUGJY)

Goals, Objectives and Benefits of Project:

1. Erection & commissioning of 5Nos 33/11KV Substation in Varanasi.
2. Erection & commissioning of addition 5Nos 5MVA Power Transformer in Varanasi along with bay.
3. Augmentation of 13 Nos old (5MVA/8MVA) Power Transformer to 10 MVA along with accessories.
4. Erection of 38.72Ckm New 33KV line, 40.009CKm New 11KV, 60.11 Ckm reconductoring.
5. 6 Nos substation R&M Work.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Manoj Kumar Agarhari ee.edivns@yahoo.com 9450963535 E.E-1st Division
L.P. Chakarvedi eeedd2vns@gmail.com 9450963530 2nd Executive Engineer
Vikash Kapoor dgmedcvns@gmail.com 8004927071 Superintending Engineer

 PROJECT DATES
Project Planned Start Date: 19/Oct/2016 Project Planned Completion Date: 31/Aug/2018

 METRICS
Key Metrics Current Planned
Erection & commissioning of 5Nos 33/11 KB sub station 1 Nos sub station (Garthauli) commissioned in SEP 2017 & rest all 4 are construction 1 Nos sub station facility will be commissioned NOV 2017, 2 Nos 2017 & 1 Nos in Feb 2018
18 Nos power transformer augmentation 6 Nos augmentation & 8 Nos are under process 4 Nos will be completed in Nov 2017, 5 Nos in Jan 2018, 3 Nos in Feb 2018

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 33/11 KV New SS-Garthauli
TaskDescriptionStart Date End DateStatus
Land Acquisition & GTP approval 1- Land acquired by electricity department and provided to LNT.
2- Guaranteed Technical Particulars (GTP) and Field Quality Plan (FQP) approved by the electricity department
08/01/2017 08/02/2017 100%
Civil work 1- Leveling of land
2- Foundation
3- Boundary wall surrounding of acquired land.
4- White wash
13/02/2017 20/08/2017 100%
Electrical Work, Switch-gear / Swithyard 1. Establishing the first phase equipment.
2. Establishing 5MVA transformer.
3. Configuration of insulator and cables.
20/08/2017 12/09/2017 100%
Pre Commissioning & Commissioning 1- Linking substation with 33KV.
2- Energize transformer for produce 11KV.
10/09/2017 15/09/2017 100%
1- Land Acquisition & GTP approval
2- Civil Works
3- Electrical Works
4- Pre Commissioning & Commissioning
5- Target of electricity department 24 hours supply to 18 villages by the
substation and separation of feeder for all 18 villages.
a) Barthara khurda
b) Ajaanv
c) Paranapur
d) Chittampur
e) Kadipur kalan
f) Gartholi(Substation)
g) Palakha
h) Bahadurpur
i) Behrampur
k) Hariharpur
l) Mathiya
m) Kursiya
n) Dhourhara
o) Tekuri
p) Duduwa
q) Saraiya
r) Bhagwanpur
19/10/2016 19/09/2017 - 100%
2 33/11 KV New SS-Rajipur
TaskDescriptionStart Date End DateStatus
Land Acquisition & GTP approval 1- Land acquired by electricity department and provided to LNT.
2- Guaranteed Technical Particulars (GTP) and Field Quality Plan (FQP) approved by electricity department.
28/02/2017 29/03/2017 100%
Civil Works 1- Leveling of land
2- Foundation
3- Boundary wall surrounding acquired land.
4- Whitewash
02/04/2017 20/10/2017 95%
Electrical Works 1. Establishing the first phase equipment.
2. Establishing 5MVA transformer.
3. Configuration of insulator and cables.
05/10/2017 22/10/2017 95%
Pre Commissioning & Commissioning 1- Pre Commissioning & Commissioning is pending still now due to lacking of Row & 33KV Cable while it's completion date was 25.10.2017 22/10/2017 25/10/2017 50%
All works completed.
Commissioning will be done in Dec 2017
19/10/2016 25/11/2017 - 100%
3 33/11 KV New SS-Betawar
TaskDescriptionStart Date End DateStatus
Land Acquisition & GTP Approval 1- Land acquired by electricity department and provided to LNT.
2- Guaranteed Technical Particulars (GTP) and Field Quality Plan (FQP) approved by the electricity department
10/05/2017 10/06/2017 100%
Civil Works 1- Leveling of land
2- Foundation
3- Boundary wall surrounding of acquired land.
4- Whitewash.
12/06/2017 20/12/2017 90%
Electrical Works 1. Establishing the first phase equipment.
2. Establishing 5MVA transformer.
3. The configuration of insulator and cables.
05/11/2017 15/12/2017 75%
Pre Commissioning & Commissioning 1- Linking substation with 33KV is pending(Commissioning).
2- Energize transformer for produce 11KV is pending
13/12/2017 18/12/2017 0%
1- Land Acquisition & GTP approval-complete
2- Civil Works-complete
3- Electrical Works-in progress
4- Pre Commissioning & Commissioning
5- Reduce the break-down or fault of light and improve the efficiency.
19/10/2016 20/01/2018 - 95%
4 33/11 KV New SS-Kardhana
TaskDescriptionStart Date End DateStatus
Land Acquisition & GTP approval 1- Land acquired by electricity department and provided to LNT.
2- Guaranteed Technical Particulars (GTP) and Field Quality Plan (FQP) approved by the electricity department
20/08/2017 20/09/2017 100%
Civil Works 1- Leveling of land
2- Foundation
3- Boundary wall surrounding of acquired land.
4- Whitewash
22/09/2017 28/02/2018 90%
Electrical Works 1. Establishing the first phase equipment.
2. Establishing 5MVA transformer.
3. The configuration of insulator and cables.
15/02/2018 25/02/2018 25%
Pre Commissioning & Commissioning 1- Linking substation with 33KV is pending(Commissioning).
2- Energize transformer for produce 11KV is pending
26/02/2018 28/02/2018 0%
1- Land Acquisition & GTP approval-complete
2- Civil Works-complete
3- Electrical Works-in progress
4- Pre Commissioning & Commissioning
5- Reduce the break-down or fault of light and improve the efficiency.
01/01/1970 01/01/1970 - 85%
5 SS augmentation along with accessories-III
TaskDescriptionStart Date End DateStatus
Transformer Augmentation Planned completion date of Transformer Augmentation was 31.10.17 but it has been completed 85% on date 22.11.2017 06/03/2017 22/11/2017 85%
Electrical Works Planned completion date of Electrical Works was 06.09.2017 but work has been completed 100% on date 10.09.2017 08/03/2017 10/09/2017 100%
Pre Commissioning & Commissioning Planned date of Pre Commissioning & Commissioning was 12.10.2017 but it has been completed 100% on date 15.10.2017 17/05/2017 15/10/2017 100%
6 Substation augmentation along with accessories-
1- Ugapur- Complete
2- Newada- complete
3- Thatra- Complete
4- Barki- Complete
5- Barni-Complete
6- Todarpur-Complete
21/11/2017 31/08/2018 - 100%
6 SS augmentation along with accessories-II
TaskDescriptionStart Date End DateStatus
Transformer Augmentation Planned completion date of Transformer Augmentation. 25/11/2017 25/12/2017 0%
Electrical Works Planned completion date of Electrical Works is 31.12.2017 and work has been
completed 60% on date 21.11.2017
14/11/2017 31/12/2017 60%
Pre Commissioning & Commissioning The planned completion date of Pre Commissioning & Commissioning. 03/01/2018 10/01/2018 0%
4 Substation augmentation along with accessories-
1- Anai-complete
2- Lalpur
3- Gajokhar
4- Sindhora
14/11/2017 10/01/2018 - 30%
7 SS augmentation along with accessories-I
TaskDescriptionStart Date End DateStatus
Transformer Augmentation Transformer Augmentation is pending. 03/01/2018 02/03/2018 0%
Electrical Works Electrical Works in progress and has been completed 45% 15/01/2017 10/03/2018 45%
Pre Commissioning & Commissioning Need to be Pre Commissioning & Commissioning according to given date 12/03/2018 25/03/2018 0%
5 Substation augmentation along with accessories-
1- Haraua
2- Pallipatti
3- Sevapuri-Complete
4- Lalpur
5- Christnagar
15/01/2017 25/03/2018 - 20%
8 SS augmentation along with accessories-IV
TaskDescriptionStart Date End DateStatus
Transformer Augmentation Need to be Start 05/02/2018 15/04/2018 0%
Electrical Work Need to be start 07/02/2018 12/04/2018 0%
Pre Commissioning & Commissioning Need to be start 17/04/2018 15/05/2018 0%
3 Substation augmentation along with accessories-
1- Jhalupur
2- Dhindaspur
3- Jhakini
05/02/2018 15/05/2018 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
4495 Lac. 0 Lac. 0 Lac. 1005 Lac. 3490 Lac.