PROJECT NAME : Installation Of Surveillance Camera on 720 Location of the City. |
Project Detail / Brief Description:
Camera Installation are in progress different location in city. |
Project Department: Smart City Varanasi |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
Sunil Kumar | mail@varanasismartcity.gov.in | ||
Rajesh Kumar Trivedi | rajesh.trivedi@repl.global | 8840994640 | Construction Manager, PMC-VSCL |
Amrendra Tiwari | mail@varanasismartcity.gov.in | 9771410338 | Senior Engineer |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 15/Jul/2020 | Project Planned Completion Date: 30/Jun/2021 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Duct laying | Work in progress | 01/08/2020 | 31/10/2021 | - | 74% |
2 | Fiber laying | WIP | 01/09/2020 | 31/10/2021 | - | 15% |
3 | Pole foundation casting | WIP | 01/03/2021 | 31/10/2021 | - | 80% |
4 | Pole erection | WIP | 01/03/2021 | 31/10/2021 | - | 55% |
5 | Earthing | WIP | 01/11/2020 | 31/10/2021 | - | 60% |
6 | RSU installation | WIP | 01/11/2020 | 31/10/2021 | - | 50% |
7 | Camera Installation | WIP | 01/06/2021 | 31/10/2021 | - | 20% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
12804 Lac. | 0 Lac. | 12804 Lac. | 4385 Lac. | 8419 Lac. |