PROJECT NAME :  Investigation & Condition Assessment Followed by Rehabilitation of Old Trunk Sewer in Varanasi by Trenchless Technology (Package- 4)
Project Detail / Brief Description:

Investigation & Condition Assessment followed by Rehabilitation of Old Trunk Sewer in Varanasi by Trenchless Technology (Package- 4)


Project Department:

Ganga Pollution Prevention Unit, U.P. Jal Nigam

Associated Yojna Name:

GANGA Action Plan - II

Goals, Objectives and Benefits of Project:

1. Zero discharge of Sewage water in River Ganga and River Varuna
2. Total 1 Lakhs house hold connected to the sewerage line available after this project.
3. Reduction of water generated diseases, generation of fertilizer and treated water for crops
4. Cleanliness driving more pilgrimage and Tourist, for Holy dip in Ganges.
5. Easy to process treated water of Ganges into Drinking water.
6. Reduction in viral and water generated diseases like Japanese encephalitis etc.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
S.K. Burman ganga@gmail.com 9450596859

 PROJECT DATES
Project Planned Start Date: 10/Jul/2015 Project Planned Completion Date: 15/May/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Rehabilitation of Old Trunk Sewer
TaskDescriptionStart Date End DateStatus
Laying of Diversion pipe line from Machhodari Park to Bhadau Chungi Completed 06/05/2020 30/11/2020 100%
De-silting from Bhadau chungi to Konia special Manhole Completed 20/11/2020 15/03/2021 100%
GRP lining from Bhadau Chungi to Konia special Manhole. Completed. 25/01/2021 31/03/2021 100%
De-silting from Machchhodari park to Bhadau chungi De-silting completed. 15/09/2021 30/04/2022 100%
GRP lining from Machchhodari Park to Bhadau Chungi. 346 lining has been completed on 06.05.2022. Balance lining in length of 650 mtrs is in progress and targeted to be completed by 31.05.2022 15/11/2021 31/05/2022 75%
Rehabilitation of Old Trunk Sewer(OTS) by GRP lining. 10/07/2015 31/05/2022 - 96%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
8458 Lac. 0 Lac. 6674 Lac. 6674 Lac. 1784 Lac.