Project Details

PROJECT NAME :  PMAY Yojana (Site 2) 608 unit, Harhua
Project Detail / Brief Description:


Project Department:

Varanasi Development Authority (VDA)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Anil Dubey 7518102825 A.E.
Chandrasekhar Ji Project Manager (Sai Baba Infra Project Pvt. Ltd.)
Narendra Singh executive_engineer@gmail.com 7518102821 Executive Engineer (Nirman)

 PROJECT DATES
Project Planned Start Date: 30/May/2018 Project Planned Completion Date: 08/Nov/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Excavation (खुदाई )
COMPLETED ( ब्लॉक ६ से १ तक ) 15/05/2019 01/08/2019 - 100%
2 Footing (फोडेशन वर्क )
COMPLETED (ब्लॉक ६ से १ तक ) 15/11/2019 01/01/2020 - 100%
3 Up to Plinth (टाई बीम)
COMPLETED 02/02/2020 01/03/2020 - 100%
4 RCC Frame Work (आरसीसी फ्रेम वर्क)
Block 6 ground to 3rd floor का कार्य पूर्ण हो चूका है 01/06/2020 15/07/2020 - 100%
5 RCC frame work (आरसीसी फ्रेम वर्क)
Block 5 ground to 3rd floor का कार्य लगभग पूर्ण हो चूका है 15/07/2020 15/09/2020 - 90%
6 Rcc frame Work (आरसीसी फ्रेम वर्क)
Block ground floor columns and slab का कार्य अभी चल रहा है
20/08/2020 20/12/2020 - 15%
7 Brick work (चिनाई कार्य )
Block 6 ground to 3rd floor का कार्य अभी चल रहा है 15/08/2020 15/12/2020 - 15%
8 Brick work (चिनाई कार्य )
Block 5 ground to 3rd floor का कार्य अभी चल रहा है
20/08/2020 20/12/2020 - 15%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
3832.45 Lac. 0 Lac. 793 Lac. 793 Lac. 3039.45 Lac.