PROJECT NAME :  132/33 KV GIS Substation Alaipur Varanasi
Project Detail / Brief Description:

The Project comprises of two parts:-
1. Construction of 132/33 KV S/s Alaipur at Erstwhile IDH premises, Kazzakpura, Varanasi.
2. Construction of 132 KV Sahupuri(220)-Sarnath LILO at Alaipur line:- This line has 02 sections, (A)Monopole section of approx. 08 Nos of towers and (B) Lattice tower section of approx. 25 Nos. of towers.


Project Department:

U.P. Power Transmission Corporation Limited (UPPTCL)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

To ensure uninterrupted and quality power supply to Kajjakpura Town Hall Kashi Deenapur Areas


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Mk Agrawal czedvns@gmail.com 9415301234
Indrabhan singh mukesh06kumar@gmail.com 9415311043

 PROJECT DATES
Project Planned Start Date: 24/Jul/2019 Project Planned Completion Date: 30/Nov/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
Erection of 6 No Tower has been done during this p 01/04/2022 15/04/2022 95%
Pile foundation work started on Loc No 33 .Minimum 16/04/2022 30/04/2022 25%
The Boundary wall work will be completed by 95%. T 01/01/2021 15/01/2021 95%
The Underground Cables will be shifted to the new 01/01/2021 15/01/2021 95%
Earth resistivity test and Topography. 01/01/2021 15/01/2021 85%
The boundry wall will be completed except the port 01/01/2021 15/01/2021 85%
Left over work of Shifting of ug cable,Transformer 01/01/2021 15/01/2021 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Handover of land from Nagar Nigam, Completion of Boundary Wall and Shifting of underground discom cables.
Boundary Wall is almost completed . Construction of Approach road and main gate is under progress. 08/01/2020 31/05/2022 - 95%
2 Soil testing, Earth resistivity test, Topography & layout finalization .
Soil testing, Earth resistivity test ,plan layout has been finilised and approved and accordingly Earth mate Drawing has been approved. 19/10/2020 31/01/2022 - 100%
3 Construction of 132KV Shahupuri - Sarnath (132KV) LILO @ Alaipur.
foundation work of line is in progress.13/33 foundation has completed.Erection of 7 No Tower has benn comlpeted.Foundation of Monopole started at Loc no. 33. 17/03/2021 20/04/2022 - 25%
4 Civil works
The civil work will include construction of 132 KV & 33 KV GIS buildings, indoor and outdoor cable trenches, Transformer and other equipment's foundation, road inside the substation's premises, official buildings etc.
Main building foundation work completed and other work is in progress.
15/11/2020 20/04/2022 - 12%
5 Electrical work Part A
Erection, testing and commissioning of 02 nos Power T/fs and 01 Nos Station Transformer. 01/05/2021 30/03/2022 - 1%
6 Electrical work Part B
Erection ,testing and commissioning of GIS modules, LCC Panels, Relay Panels, Batteries etc to be installed in 132 KV GIS Hall. 21/05/2021 30/03/2022 - 1%
7 Electrical work Part C
1. Erection, testing and commissioning of GIS modules and other equipment's to be installed in 33 KV GIS Hall.
2.Testing and commissioning of SCADA system.
05/06/2021 30/03/2022 - 1%
8 Installationof fire fighting equipments
Installation of Fire Hydrants/Emulsifier/ Fire huts etc. 15/05/2021 30/03/2022 - 1%
9 Construction of Cable Trenches for Underground Power/Control Cables.
Construction of Power/Control Cable trenches 01/06/2021 30/03/2022 - 1%
10 Miscellaneous leftover works.
The various leftover works (if any) will be done in this period. 01/09/2021 30/03/2022 - 1%
11 Testing and Energization
All the equipment will be tested and the substation will be charged after getting clearance from Electrical safety. 16/09/2020 30/03/2022 - 1%
12 Construction of substation main building is under process.
TaskDescriptionStart Date End DateStatus
Construction of Line (12T+0MP/25T+8MP) . 12 No Foundation work has been completed. 01/12/2021 30/06/2022 20%
Substation main building construction started. Boubdery wall of sub station comlpeted.Earthmat drawing of Electrical has Approved. 10/04/2021 30/03/2022 - 3%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
5605 Lac. 0 Lac. 735.15972 Lac. 735.15972 Lac. 4869.84028 Lac.