PROJECT NAME : 16 Court Room in District Court Varanasi |
Project Detail / Brief Description:
16 Court Room in District Court Varanasi (G+8 structure) |
Project Department: Construction & Design Services (C&DS) Unit-24,U.P Jal Nigam |
Associated Yojna Name: 16 Court Room in district court Varanasi |
||
Goals, Objectives and Benefits of Project:
To Provide The New Courtroom to Judge. |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
Yogesh kumar Gupta | pm24.vns@gmail.com | 9170637641 |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 08/Feb/2015 | Project Planned Completion Date: 28/Feb/2021 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
Building work. | 01/02/2021 | 15/02/2021 | 95% |
Plaster Work | 01/02/2021 | 15/02/2021 | 100% |
Brick Work 6th & 7th Floor | 01/02/2021 | 15/02/2021 | 100% |
Brick Work 6th & 7th Floor | 01/02/2021 | 15/02/2021 | 100% |
Brick Work 6th & 7th Floor | 01/02/2021 | 15/02/2021 | 100% |
Brick Work 6th & 7th Floor | 01/02/2021 | 15/02/2021 | 100% |
Brick Work 6th & 7th Floor | 01/02/2021 | 15/02/2021 | 100% |
Brick Work 6th & 7th Floor | 01/02/2021 | 15/02/2021 | 100% |
Brick Work 6th & 7th Floor | 01/02/2021 | 15/02/2021 | 100% |
Brick Works 6th & 7th Floor | 01/02/2021 | 15/02/2021 | 100% |
Brick Works at 6th & 7th Floor | 01/02/2021 | 15/02/2021 | 100% |
Seventh Floor Balance Roof | 01/02/2021 | 15/02/2021 | 100% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Construction of Court Building (G+8) | Work completed | 01/02/2015 | 31/12/2018 | - | 100% |
2 | Infrastructure Works | Work started in March, 2020 | 01/03/2018 | 31/12/2019 | - | 85% |
3 | This is for testing | THis is only for demo | 29/07/2019 | 29/08/2019 | - | 10% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
3283.79 Lac. | 0 Lac. | 3118.66 Lac. | 3118.66 Lac. | 165.13 Lac. |