PROJECT NAME : 2 Megawatt Solar Power Plant Construction in Bhelupur Water Works Campus |
Project Detail / Brief Description:
Due to land issue, project may be delayed my 3 months.Site was handed over to contractor on 24/12/2021 and LOA issued on 21/05/2021. |
Project Department: Ganga Pollution Prevention Unit, U.P. Jal Nigam |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
S.K. Burman | ganga@gmail.com | 9450596859 |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 01/May/2021 | Project Planned Completion Date: 30/Sep/2022 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | SITC of 2 MW solar power project | Solar work at bhelupur | 22/03/2022 | 31/07/2022 | - | 40% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
1724 Lac. | 0 Lac. | 695 Lac. | 516.3 Lac. | 1207.7 Lac. |