Project Details

PROJECT NAME :  City Gas Distribution Varanasi
Project Detail / Brief Description:

GAIL (India) Limited Authorized to create piped Natural gas network to households and CNG stations to supply economically, green fuel to vehicles in Varanasi City.


Project Department:

Gas Authority of India Limited (GAIL)

Associated Yojna Name:

Pradhan Mantri Urja Ganga Pariyojana

Goals, Objectives and Benefits of Project:

With an aim to provide uninterrupted access of cleaner and quality energy to Eastern & North Eastern part of the country, gas pipeline projects Jagdishpur – Haldia & Bokaro – Dhamra/ Barauni- Guwahati Pipeline Project (JHBDPL/BGPL) popularly known as the Pradhan Mantri Urja Ganga (PMUG), of total length of 3291 Km are being executed at a cost of approx. Rs. 13,000 Crore.
Government of India is providing a Capital Grant of Rs 5,176 Crores (40% of the project cost) for timely completion of the project by 2020. This pipeline project will cater to the energy requirements of the States of Uttar Pradesh, Bihar, Jharkhand, West Bengal, Odisha and Assamcovering 70 Districts and 3150 Villages.
Along with development of the JHBDPL project, six (06) City Gas Distribution Network (CGD) projects viz Varanasi, Patna, Jamshedpur, Ranchi, Bhubaneswar and Cuttack en-route of pipeline are also being executed. In addition, 15 new Geographical Areas covering 34 districts en-route of Urja Ganga project have been offered for award of CGD projects under the ongoing 9th CGD bidding round.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
N K Dwivedi gaurishanker@gail.co.in 9999037537 DGM

 PROJECT DATES
Project Planned Start Date: 30/Apr/2017 Project Planned Completion Date: 31/Mar/2023

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Laying of steel pipeline 75 km
TaskDescriptionStart Date End DateStatus
CUMULATIVE STEEL LAYING -75KM CUMULATIVE STEEL PIPE LAYING TARGET-75KM,ACHIEVED 77KM 01/04/2018 31/03/2022 100%
LAYING CUMMULATIVE 75KM .Completed. 01/04/2018 31/03/2022 - 100%
2 Laying of MDPE Pipline-500 Km
Cumulative Laying of Different Size of MDPE Pipeline-Total Laid -500 Km as on date 01/04/2018 31/03/2022 - 100%
3 GI Infrasture-50000
CUMULATIVE GI INFRASTRUCTURE-49840 ACHIEVED AS ON DATE 01/04/2018 31/03/2022 - 99%
4 CNG Stations-28
28 CNG Station mechanically completed, out of which 16 are in operation 01/04/2018 31/03/2022 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
34500 Lac. 0 Lac. 33800 Lac. 25000 Lac. 9500 Lac.