Back     

Project Details

PROJECT NAME :  Community Health Center Sarnath Varanasi
Project Detail / Brief Description:


Project Department:

U.P. State Construction & Infrastructure Development Corporation Ltd.

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Aniruddhu Prasad varanasi.upsknn@rediffmail.com 9454455973

 PROJECT DATES
Project Planned Start Date: 24/Jun/2020 Project Planned Completion Date: 31/Mar/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
First Floor RLD 16/03/2021 31/03/2021 80%
Ground Floor 16/03/2021 31/03/2021 100%
RCC work in Foundation 16/03/2021 31/03/2021 100%
Excavation in foundation 01/01/2021 15/01/2021 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Excavation in Foundation
Excavation in Foundation 100% Completed up to Dated 30.11.2020 01/08/2020 30/11/2020 - 100%
2 RCC Work in Foundation
RCC Work in Foundation 07/08/2020 15/02/2021 - 100%
3 Ground Floor
Ground Floor Slab complete, Chinaai complete, Internal plaster work complete, Outer side wall stone work 85% complete, internal wall tiles work 75% complete, sanitary & Water Supply work 25% complete, Boundrywall not start
Note :- Work Stop Due to Fund Not Recieved Rs. (667.22-330.90) = Rs. 336.32 Lacs
01/11/2020 23/03/2022 - 70%
4 First Floor
First Floor Slab complete, Chinaai complete, Internal plaster work complete, Outer side wall stone work 75% complete, internal wall tiles work 75% complete, sanitary & Water Supply work 25% complete
Note :- Work Stop Due to Fund Not Recieved Rs. (667.22-330.90) = Rs. 336.32 Lacs
01/11/2021 23/02/2022 - 70%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
681 Lac. 0 Lac. 331 Lac. 303 Lac. 378 Lac.



Back