PROJECT NAME :  Construction of 32 room hostel/barrak & 1 scrutiny room in Thana Rohania
Project Detail / Brief Description:

विवेचना कक्ष/बैरक का निर्माण कार्य पूर्ण। हस्तान्तरण की कार्यवाही प्रगति में।


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 01/Aug/2020 Project Planned Completion Date: 30/Apr/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
external site development work will complete withi 16/04/2022 30/04/2022 100%
Construction of Septic tank has been completed and 16/04/2022 30/04/2022 100%
Painting and distempering work in inner wall is in 16/03/2022 31/03/2022 100%
internal water supply and fitting work is in progr 16/03/2022 31/03/2022 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 internal plumbing works
internal plumbing works will be completed as per schedule 12/03/2022 30/03/2022 - 100%
2 Painting works
Painting works will be completed as per schedule 18/03/2022 05/04/2022 - 30%
3 External Sewerage works
Septic tank works is in progress 05/03/2022 10/04/2022 - 60%
4 External Site development
External Site development will be completed as per schedule 05/04/2022 15/04/2022 - 1%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
115.47 Lac. 0 Lac. 115.47 Lac. 115 Lac. 0.47 Lac.