PROJECT NAME : Construction of 80 flats (Package-II) in Jodhpur Colony BHU, Varanasi |
Project Detail / Brief Description:
Construction of 80 flats (Package-II) for faculties at BHU, Varanasi. |
Project Department: Central Public Works Department (CPWD) |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
ASHOK KUMAR GUPTA | eevpd@rediffmail.com | 9999798241 | Project Head |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 27/Feb/2020 | Project Planned Completion Date: 31/Aug/2021 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
External and internal finishing, flooring, SS work | 01/08/2021 | 15/08/2021 | 70% |
RCC structure and brick work completed | 16/02/2021 | 28/02/2021 | 100% |
RCC structure and brick work completed | 01/08/2021 | 15/08/2021 | 100% |
Level 9- 50% slabs to be completed as per target. | 01/02/2021 | 15/02/2021 | 100% |
Level 8- balance 50% slabs to be completed | 01/02/2021 | 15/02/2021 | 100% |
Level 8 - 50% slab as per target completed | 01/01/2021 | 15/01/2021 | 100% |
Level 7 slab completed | 01/01/2021 | 15/01/2021 | 100% |
Level 6 slab completed | 01/01/2021 | 15/01/2021 | 100% |
Level 5 slab completed and sample unit under progr | 16/10/2020 | 31/10/2020 | 100% |
Level 4 slab completed | 01/10/2020 | 15/10/2020 | 100% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | 1st mile stone | Foundation work is to be completed up to plinth level. Target achieved. | 27/02/2020 | 15/08/2020 | - | 100% |
2 | 2nd Milestone | RCC Structure to be completed upto G+3 targets achieved. | 16/08/2020 | 31/10/2020 | - | 100% |
3 | 3rd Milestone | Targets : Structure : up to level 9 Brick work : up to level 7 Finishing: up to level 6 targets achieved. | 01/11/2020 | 31/01/2021 | - | 100% |
4 | 4th mile stone | All RCC work completed. Brick work completed. | 01/02/2021 | 31/03/2021 | - | 100% |
5 | 5th milestone | Finishing works are under progress. | 01/04/2021 | 31/08/2021 | - | 70% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
6063 Lac. | 0 Lac. | 4226 Lac. | 2786 Lac. | 3277 Lac. |