PROJECT NAME :  Construction of Barrack for 200 person in PAC Ramnagar
Project Detail / Brief Description:

भू-तल एवं प्रथम तल तथा द्वितीय तल के छत का कार्य पूर्ण तृतीय तल के कॉलम व छत का कार्य पूर्ण। प्रथम तक, द्वितीय तल एवं तृतीय तल में ब्रिक वर्क का कार्य प्रगति में तथा जी0$4 के कॉलम का कार्य प्रगति में। पूर्व में धनाभाव के कारण प्रगति धीमी है।


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 01/Dec/2020 Project Planned Completion Date: 31/May/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
5th floor slab will be casted in next 15 days 16/04/2022 30/04/2022 100%
Slab of 4th floor will be casted till 31st March 2 16/03/2022 31/03/2022 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 3rd floor RCC Frame Structure
Slab casting will be completed by 31st March 18/03/2022 31/03/2022 - 60%
2 4th floor RCC Frame Structure
Column work for 4th floor will be stated from 2 April and slab will be completed till 14 April 02/04/2022 14/04/2022 - 1%
3 5th floor RCC Frame Structure
Column work for 5th floor will be stated from 16 April and slab will be completed till 28 April 15/04/2022 28/04/2022 - 0%
4 6th floor RCC Frame Structure
Column work for 6th floor will be stated from 30 April and slab will be completed till 15 May 30/04/2022 15/05/2022 - 0%
5 7th floor RCC Frame Structure
7th Floor RCC Frame Structure will be completed within scheduled timeline 16/05/2022 31/05/2022 - 0%
6 8th floor RCC Frame Structure
8th Floor RCC Frame Structure will be completed within scheduled timeline 01/06/2022 15/06/2022 - 0%
7 9th floor RCC Frame Structure
8th Floor RCC Frame Structure will be completed within scheduled timeline 17/06/2022 30/06/2022 - 0%
8 10th floor RCC Frame Structure
10th Floor RCC Frame Structure will be completed within scheduled timeline 02/07/2022 15/07/2022 - 0%
9 11th floor RCC Frame Structure
11th Floor RCC Frame Structure will be completed within scheduled timeline 17/07/2022 31/07/2022 - 0%
10 Brick Work
Brick Work will be completed within scheduled timeline 01/11/2021 31/07/2022 - 0%
11 Flooring Work
Flooring Work will be completed within scheduled timeline 01/05/2022 05/08/2022 - 0%
12 Plastering and Painting Work
Plastering and Painting Work will be completed within scheduled timeline 01/06/2022 20/08/2022 - 0%
13 Electrification and Firefighting Works
Electrification and Firefighting Works will be completed within scheduled timeline 15/06/2022 31/07/2022 - 0%
14 Utility Installation
Utility Installation will be completed within scheduled timeline 15/08/2022 31/08/2022 - 0%
15 Doors and window Fittings
Doors and window Fittings will be completed within scheduled timeline 01/07/2022 25/08/2022 - 0%
16 Internal Plumbing Works
Internal Plumbing Works will be completed within scheduled timeline 01/06/2022 20/08/2022 - 0%
17 External Sewerage Works
External Sewerage Works will be completed within scheduled timeline 15/07/2022 25/08/2022 - 0%
18 External Site Development and Approach Road
External Site Development and Approach Road will be completed within scheduled timeline 01/08/2022 31/08/2022 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1002.55 Lac. 0 Lac. 420.63 Lac. 398 Lac. 604.55 Lac.