SCHEDULE |
Sr. |
Milestone |
Description |
Start Date |
Planned Completion Date |
Actual Completion Date |
Milestone Completion(In %) |
1 | 4th floor RCC Frame Structure
| Slab casting will be completed till 31st March | 18/03/2022 | 31/03/2022 | - | 60% |
2 | 5th floor RCC Frame Structure
| column work for 5th floor will be started from 2 April and slab will be completed till 15 April. | 02/04/2022 | 15/04/2022 | - | 0% |
3 | 6th floor RCC Frame Structure
| 6th floor RCC Frame Structure will be completed within scheduled timeline | 17/04/2022 | 30/04/2022 | - | 0% |
4 | 7th floor RCC Frame Structure
| 7th floor RCC Frame Structure will be completed within scheduled timeline | 02/05/2022 | 20/05/2022 | - | 0% |
5 | 8th floor RCC Frame Structure
| 8th floor RCC Frame Structure will be completed within scheduled timeline | 22/05/2022 | 05/06/2022 | - | 0% |
6 | 9th floor RCC Frame Structure
| 9th floor RCC Frame Structure will be completed within scheduled timeline | 07/06/2022 | 20/06/2022 | - | 0% |
7 | 10th floor RCC Frame Structure
| 10th floor RCC Frame Structure will be completed within scheduled timeline | 22/06/2022 | 05/07/2022 | - | 0% |
8 | 11th floor RCC Frame Structure
| 11th floor RCC Frame Structure will be completed within scheduled timeline | 07/07/2022 | 22/07/2022 | - | 0% |
9 | Brick work
| Brick work will be completed within scheduled timeline | 01/11/2021 | 31/07/2022 | - | 0% |
10 | Flooring Work
| Flooring Work will be completed within scheduled timeline | 01/05/2022 | 05/08/2022 | - | 0% |
11 | Plastering and Painting Work
| Plastering and Painting Work will be completed within scheduled timeline | 01/06/2022 | 20/08/2022 | - | 0% |
12 | Electrification and fire fighting work
| Electrification and fire fighting work will be completed within scheduled timeline | 15/06/2022 | 20/07/2022 | - | 0% |
13 | utility installation will be completed
| utility installation will be completed within scheduled timeline | 15/08/2022 | 31/08/2022 | - | 0% |
14 | Doors and window fittings
| Doors and window fittings will be completed within scheduled timeline | 01/07/2022 | 25/08/2022 | - | 0% |
15 | Internal Plumbing works
| Internal Plumbing works will be completed within scheduled timeline | 01/06/2022 | 20/08/2022 | - | 0% |
16 | External Sewerage Works
| External Sewerage Works will be completed within scheduled timeline | 15/07/2022 | 25/08/2022 | - | 0% |
17 | External Site Development and Approach road
| External Site Development and Approach road will be completed within scheduled timeline will be completed within scheduled timeline | 01/08/2022 | 31/08/2022 | - | 0% |