Project Details

PROJECT NAME :  Construction of Barrack for 200 person in PAC Bhullanpur
Project Detail / Brief Description:

1-भूतल के स्लैब की ढलाई एवं दिवारों की चिनाई का कार्य पूर्ण । 2- प्रथम तल के स्लैब की ढलाई एवं दिवारों की चिनाई का कार्य पूर्ण । 3-द्वितीय तल के स्लैब की ढलाई एवं दिवारों की चिनाई का कार्य पूर्ण । 4-तृतीय तल के स्लैब की ढलाई एवं दिवारों की चिनाई का कार्य पूर्ण । 5- चतुर्थ तल के स्लैब की ढलाई एवं दिवारों की चिनाई का कार्य पूर्ण । 6- पंचम तल के स्लैब ढलाई का कार्य पूर्ण। 7-कॉलम की ढलाई का कार्य प्रगति में।


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 01/Dec/2020 Project Planned Completion Date: 31/May/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
5th floor slab will be casted in next 15 days 16/04/2022 30/04/2022 100%
Slab of 4th floor will be casted till 31st March 2 16/03/2022 31/03/2022 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 4th floor RCC Frame Structure
Slab casting will be completed till 31st March 18/03/2022 31/03/2022 - 60%
2 5th floor RCC Frame Structure
column work for 5th floor will be started from 2 April and slab will be completed till 15 April. 02/04/2022 15/04/2022 - 0%
3 6th floor RCC Frame Structure
6th floor RCC Frame Structure will be completed within scheduled timeline 17/04/2022 30/04/2022 - 0%
4 7th floor RCC Frame Structure
7th floor RCC Frame Structure will be completed within scheduled timeline 02/05/2022 20/05/2022 - 0%
5 8th floor RCC Frame Structure
8th floor RCC Frame Structure will be completed within scheduled timeline 22/05/2022 05/06/2022 - 0%
6 9th floor RCC Frame Structure
9th floor RCC Frame Structure will be completed within scheduled timeline 07/06/2022 20/06/2022 - 0%
7 10th floor RCC Frame Structure
10th floor RCC Frame Structure will be completed within scheduled timeline 22/06/2022 05/07/2022 - 0%
8 11th floor RCC Frame Structure
11th floor RCC Frame Structure will be completed within scheduled timeline 07/07/2022 22/07/2022 - 0%
9 Brick work
Brick work will be completed within scheduled timeline 01/11/2021 31/07/2022 - 0%
10 Flooring Work
Flooring Work will be completed within scheduled timeline 01/05/2022 05/08/2022 - 0%
11 Plastering and Painting Work
Plastering and Painting Work will be completed within scheduled timeline 01/06/2022 20/08/2022 - 0%
12 Electrification and fire fighting work
Electrification and fire fighting work will be completed within scheduled timeline 15/06/2022 20/07/2022 - 0%
13 utility installation will be completed
utility installation will be completed within scheduled timeline 15/08/2022 31/08/2022 - 0%
14 Doors and window fittings
Doors and window fittings will be completed within scheduled timeline 01/07/2022 25/08/2022 - 0%
15 Internal Plumbing works
Internal Plumbing works will be completed within scheduled timeline 01/06/2022 20/08/2022 - 0%
16 External Sewerage Works
External Sewerage Works will be completed within scheduled timeline 15/07/2022 25/08/2022 - 0%
17 External Site Development and Approach road
External Site Development and Approach road will be completed within scheduled timeline will be completed within scheduled timeline 01/08/2022 31/08/2022 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1002.7 Lac. 0 Lac. 419.67 Lac. 401 Lac. 601.7 Lac.