Project Details

PROJECT NAME :  Construction of Doctor Hostel Nurses Hostel Dharamshala and Double Basement for Mahamana Pt. Madan Mohan Malviya Cancer Center at BHU Varanasi
Project Detail / Brief Description:

This project is being constructed to provide accommodation to Doctors and Nurses of Mahamana Pt. Madan Mohan Malviya Cancer Centre BHU varanasi. Dharamshala builing is to accomodate cancers patients. Basement provisioned for parking of 520 nos vehicle of Hospital.


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

To provide accomadation to Doctor, Nurses & Patients and Parking facility for 520 nos hospital Vehicle


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Kamlesh Chandr eevaranasi@rediffmail.com 9161733777 Executive Engineer
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 10/Jan/2019 Project Planned Completion Date: 30/Jun/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
8th floor room tile work in Doctor Hostel. Sanita 01/08/2021 15/08/2021 52%
Completion of Tile flooring upto 7th floor of Nurs 16/03/2021 31/03/2021 95%
Completion of external plaster of Doctor Hostel. 01/03/2021 15/03/2021 100%
Completion of balcony railing of Nurses Hostel. C 01/03/2021 15/03/2021 100%
Completion of one side balcony railing upto 6th fl 01/03/2021 15/03/2021 100%
Completion of balcony railing 2nd floor of Nurses 01/01/2021 15/01/2021 100%
Completion of balcony railing 1st floor of Nurses 01/01/2021 15/01/2021 100%
Completion of brick work of 7th & 8th floor of Nur 01/01/2021 15/01/2021 100%
Completion of brick work of 7th & 8th floor of Nur 01/01/2021 15/01/2021 100%
Completion of RCC of 7th slab of Dharmshala Compl 16/10/2020 31/10/2020 100%
Completion of 6th floor brick work of Doctor Hoste 01/10/2020 15/10/2020 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 3rd Milestone
Completion of RCC work upto 3rd floor level including brick work upto ground floor including associated E&M works. 01/05/2020 30/09/2020 - 100%
2 4th milestone
Completion of RCC work upto 6th floor level including brick work upto 3rd floor including associated E&M works 01/10/2020 30/11/2020 - 100%
3 5th Milestone
Completion of RCC work upto terrace level including completion of connected E&M conduit work in all buildings. Brick work upto 6th floor, internal plaster, internal water supply, sanitary installation and flooring & dado work upto 4th floor. 01/12/2020 31/01/2021 - 50%
4 6th Milestone
Completion of external plaster, internal painting along with fixing of door/window frames, completion of flooring, Sanitary pipe, water supply pipe laying work & water proofing of podium slab and terrace including associated E&M works. 01/02/2021 31/03/2021 - 0%
5 7th Milestone
Completion of external painting, road work, storm water drain and sewer line, Installation of LT panels, cabling, CCTV, ventilation equipments, fire fighting and fire alarm system complete. Testing of lifts. 01/04/2021 31/05/2021 - 0%
6 8th Milestone
Completion including testing and commissioning of all work 01/06/2021 30/09/2021 - 5%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
13000 Lac. 0 Lac. 7600 Lac. 6517 Lac. 6483 Lac.