PROJECT NAME : Construction of Doctor Hostel Nurses Hostel Dharamshala and Double Basement for Mahamana Pt. Madan Mohan Malviya Cancer Center at BHU Varanasi |
Project Detail / Brief Description:
This project is being constructed to provide accommodation to Doctors and Nurses of Mahamana Pt. Madan Mohan Malviya Cancer Centre BHU varanasi. Dharamshala builing is to accomodate cancers patients. Basement provisioned for parking of 520 nos vehicle of Hospital. |
Project Department: Central Public Works Department (CPWD) |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project:
To provide accomadation to Doctor, Nurses & Patients and Parking facility for 520 nos hospital Vehicle |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
Kamlesh Chandr | eevaranasi@rediffmail.com | 9161733777 | Executive Engineer |
ASHOK KUMAR GUPTA | eevpd@rediffmail.com | 9999798241 | Project Head |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 10/Jan/2019 | Project Planned Completion Date: 30/Jun/2021 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
8th floor room tile work in Doctor Hostel. Sanita | 01/08/2021 | 15/08/2021 | 52% |
Completion of Tile flooring upto 7th floor of Nurs | 16/03/2021 | 31/03/2021 | 95% |
Completion of external plaster of Doctor Hostel. | 01/03/2021 | 15/03/2021 | 100% |
Completion of balcony railing of Nurses Hostel. C | 01/03/2021 | 15/03/2021 | 100% |
Completion of one side balcony railing upto 6th fl | 01/03/2021 | 15/03/2021 | 100% |
Completion of balcony railing 2nd floor of Nurses | 01/01/2021 | 15/01/2021 | 100% |
Completion of balcony railing 1st floor of Nurses | 01/01/2021 | 15/01/2021 | 100% |
Completion of brick work of 7th & 8th floor of Nur | 01/01/2021 | 15/01/2021 | 100% |
Completion of brick work of 7th & 8th floor of Nur | 01/01/2021 | 15/01/2021 | 100% |
Completion of RCC of 7th slab of Dharmshala Compl | 16/10/2020 | 31/10/2020 | 100% |
Completion of 6th floor brick work of Doctor Hoste | 01/10/2020 | 15/10/2020 | 100% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | 3rd Milestone | Completion of RCC work upto 3rd floor level including brick work upto ground floor including associated E&M works. | 01/05/2020 | 30/09/2020 | - | 100% |
2 | 4th milestone | Completion of RCC work upto 6th floor level including brick work upto 3rd floor including associated E&M works | 01/10/2020 | 30/11/2020 | - | 100% |
3 | 5th Milestone | Completion of RCC work upto terrace level including completion of connected E&M conduit work in all buildings. Brick work upto 6th floor, internal plaster, internal water supply, sanitary installation and flooring & dado work upto 4th floor. | 01/12/2020 | 31/01/2021 | - | 50% |
4 | 6th Milestone | Completion of external plaster, internal painting along with fixing of door/window frames, completion of flooring, Sanitary pipe, water supply pipe laying work & water proofing of podium slab and terrace including associated E&M works. | 01/02/2021 | 31/03/2021 | - | 0% |
5 | 7th Milestone | Completion of external painting, road work, storm water drain and sewer line, Installation of LT panels, cabling, CCTV, ventilation equipments, fire fighting and fire alarm system complete. Testing of lifts. | 01/04/2021 | 31/05/2021 | - | 0% |
6 | 8th Milestone | Completion including testing and commissioning of all work | 01/06/2021 | 30/09/2021 | - | 5% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
13000 Lac. | 0 Lac. | 7600 Lac. | 6517 Lac. | 6483 Lac. |