PROJECT NAME : Construction of NH-56 Bypass Varanasi Ring Road Phase - 2, Pkg - 1 |
Project Detail / Brief Description:
Project has been completed and inaugurated by Hon'ble PM on 25.10.2021 |
Project Department: National Highways Authority Of India (NHAI) |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project:
Decongestion of traffic by providing bypass to vechicles coming from NH - 2 |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
R. S. Yadav | var@nhai.org | 9984114097 | Project Director |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 15/Sep/2019 | Project Planned Completion Date: 30/Dec/2022 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
Completed on 21.10.2021 and inaugurated by Hon'ble | 16/10/2021 | 31/10/2021 | 100% |
Towards completion of Mile Stone-III. | 01/10/2020 | 15/10/2020 | 89% |
Towards completion of Mile Stone-III. | 16/09/2021 | 30/09/2021 | 82% |
Towards completion of Mile Stone-III. | 16/08/2021 | 31/08/2021 | 76% |
Towards completion of Mile Stone-III. | 16/08/2021 | 31/08/2021 | 68% |
Towards completion of Mile Stone-III. | 01/08/2021 | 15/08/2021 | 72% |
Towards completion of Mile Stone-III. | 16/07/2021 | 31/07/2021 | 69% |
Towards completion of Mile Stone-III. | 16/03/2021 | 31/03/2021 | 52% |
Towards completion of Mile Stone-III. | 01/03/2021 | 15/03/2021 | 51% |
Towards completion of Mile Stone-III. | 16/02/2021 | 28/02/2021 | 48% |
Towards completion of Mile Stone-II | 01/02/2021 | 15/02/2021 | 46% |
Towards completion of Mile Stone-II | 01/01/2021 | 15/01/2021 | 42% |
Towards completion of Mile Stone-II | 16/12/2020 | 31/12/2020 | 38% |
Towards completion of Mile Stone-II | 16/11/2020 | 30/11/2020 | 10% |
Towards completion of Mile Stone-II | 01/11/2020 | 15/11/2020 | 33% |
Towards completion of Mile Stone-II | 01/10/2020 | 15/10/2020 | 0% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Competed on 21.10.2021 and inaugurated by Hon'ble PM on 25.10.2021 | Project completed on 21.10.2021 and inaugurated by Hon'ble PM on 25.10.2021 | 15/09/2019 | 13/03/2021 | - | 100% |
2 | Milestone - III | IN PROGRESS | 15/09/2019 | 31/10/2021 | - | 70% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
101129 Lac. | 101129 Lac. | 95835 Lac. | 95835 Lac. | 106423 Lac. |