PROJECT NAME : Construction of Vaidic Vigyan Kendra Second Phase |
Project Detail / Brief Description:
Structure for main building has been completed. Flooring and finishing is in progress. Door frame fixing completed. Internal plumbing and sewer completed. Painting and Mandir work is in progress. Tile work and sanitary work is in progress. Terrace water proofing is in progress. Note : 1. Initial delay due to finalization in layout plan and late tree cutting by the BHU authority. 2. Completion date extended due to extra work since one additional is added. 3. Tentative Target Date of Completion : 30.06.2022. |
Project Department: Central Public Works Department (CPWD) |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
ASHOK KUMAR GUPTA | eevpd@rediffmail.com | 9999798241 | Project Head |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 01/Mar/2021 | Project Planned Completion Date: 30/Jun/2022 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
1. Structure completed (G+3) all. 2. Brick work | 01/05/2022 | 15/05/2022 | 90% |
1. Internal painting work 50% will be completed an | 16/03/2022 | 31/03/2022 | 90% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Sixth Milestone | 1. Completion of internal , external painting & false ceiling works. 2. Completion of external Development work (road, drainage) etc. 3. Installation of Fan and fittings in all complete. 4. Testing for Fire fighting. 5. External water supply pipe. | 15/03/2022 | 30/06/2022 | - | 10% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
934 Lac. | 0 Lac. | 934 Lac. | 448.38 Lac. | 485.62 Lac. |