Project Details

PROJECT NAME :  Construction of Varuna River Bridge Lahartara - Phoolwaria Marg Imaliyaghat in District Varanasi
Project Detail / Brief Description:

Varuna bridge on lahartara phulwaria J.P. mehta inter college via central jail via shivpur chungi marg


Project Department:

U.P. State Bridge Corporation Ltd. - Varanasi Unit

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
SANTOSH KUMAR NIRANJAN bcuvaranasi@gmail.com 8765973499 Dy. Project Manager

 PROJECT DATES
Project Planned Start Date: 01/May/2018 Project Planned Completion Date: 31/Mar/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
सेतु का कार्य पूर् 16/03/2022 31/03/2022 0%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 फ़ाउंडेशन
पूर्ण 31/03/2019 31/03/2020 - 100%
2 सब स्टृक्चर
कार्य पूर्ण है 30/04/2019 30/04/2020 - 100%
3 सुपर स्ट्रक्चर
कार्य पूर्ण है 31/12/2019 30/06/2020 - 100%
4 पहुँच मार्ग
सेतु का पुनरीक्षित आगणन मुख्यालय के पत्र सं0 607/951पीबीसी/2021 दिनांक 02.09.2021 द्वारा रू0 4494.46 लाख का मुख्य अभियन्ता (सेतु), लो0नि0वि0, लखनऊ को प्रेषित 29/02/2020 31/12/2020 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
3464.85 Lac. 0 Lac. 3291.61 Lac. 3669.39 Lac. -204.54 Lac.