Back     

Project Details

PROJECT NAME :  Construction of 80 flats (Package-II) at BHU, Varanasi
Project Detail / Brief Description:

Construction of 80 flats (Package-II) for faculties at BHU, Varanasi.


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 27/Feb/2020 Project Planned Completion Date: 31/Aug/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
Level 8 slab to be completed 01/12/2020 15/12/2020 0%
Level 6 slab and part of level 7 slab under progre 16/11/2020 30/11/2020 25%
Level 6 slab under progress. 01/11/2020 15/11/2020 50%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 1st mile stone
Foundation work is to be completed up to plinth level.
Target achieved.
27/02/2020 15/08/2020 - 100%
2 2nd Milestone
RCC Structure to be completed upto G+3 16/08/2020 31/10/2020 - 80%
3 3rd Milestone
Targets :
Structure : up to level 9
Brick work : up to level 7
Finishing: up to level 6
01/11/2020 31/01/2021 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
6061 Lac. 0 Lac. 1995.5 Lac. 779 Lac. 5282 Lac.



Back