Back     

Project Details

PROJECT NAME :  Construction of 80 flats (Package I) at BHU Varanasi
Project Detail / Brief Description:

80 nos Residential flat for faculties


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

Residential flat for Professors


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 27/Feb/2020 Project Planned Completion Date: 31/Aug/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
Level 9- 50% casting target to be completed 01/01/2021 15/01/2021 50%
Level 8 - 50% balance slabs completed 01/01/2021 15/01/2021 100%
Level 8 slab casting (50%) as per target complete 01/01/2021 15/01/2021 100%
Level 7 slab completed 01/01/2021 15/01/2021 100%
Level 6 slab completed 01/11/2020 15/11/2020 100%
Level 5 slab completed. Sample flat under finaliza 16/10/2020 31/10/2020 100%
Level 4 slab casting completed 01/10/2020 15/10/2020 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 1st mile stone
Foundation work is to be completed up to plinth level. target achieved. 27/02/2020 15/08/2020 - 100%
2 2nd Milestone
Target: RCC Structure is to be completed upto G+3
16/08/2020 31/10/2020 - 100%
3 3rd Milestone
Targets :
Structure : up to level 9
Brick work : up to level 7
Finishing: up to level 6
01/11/2020 31/01/2021 - 60%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
6061 Lac. 0 Lac. 1919.5 Lac. 1016 Lac. 5045 Lac.



Back