Project Details

PROJECT NAME :  Construction of Shree Kashi Vishwanath Temple Annakshetra, Varanasi
Project Detail / Brief Description:

Const. Of Annashatra (G+5) Building at Kashi Vishvnath Mandir, Godaulia, Varanasi


Project Department:

U.P. Awas Vikas- Construction Unit

Associated Yojna Name:

Annashatra (G+5) Building

Goals, Objectives and Benefits of Project:

To Provide food at low cost for religious people.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
J.K. Kaushal upavppm@gmail.com 8795810174 Project Manager

 PROJECT DATES
Project Planned Start Date: 02/Dec/2017 Project Planned Completion Date: 02/Dec/2018

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Foundation work
Excavation, Laying of PCC, Laying of raft 02/12/2017 31/01/2018 - 5%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
310 Lac. 0 Lac. 0 Lac. 1 Lac. 309 Lac.



Back