Project Details

PROJECT NAME :  Construction of NH-56 Bypass Varanasi Ring Road Phase - 2, Pkg - 1
Project Detail / Brief Description:

Project has been completed and inaugurated by Hon'ble PM on 25.10.2021


Project Department:

National Highways Authority Of India (NHAI)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

Decongestion of traffic by providing bypass to vechicles coming from NH - 2


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. S. Yadav var@nhai.org 9984114097 Project Director

 PROJECT DATES
Project Planned Start Date: 15/Sep/2019 Project Planned Completion Date: 14/Mar/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
Completed on 21.10.2021 and inaugurated by Hon'ble 16/10/2021 31/10/2021 100%
Towards completion of Mile Stone-III. 01/10/2020 15/10/2020 89%
Towards completion of Mile Stone-III. 16/09/2021 30/09/2021 82%
Towards completion of Mile Stone-III. 16/08/2021 31/08/2021 76%
Towards completion of Mile Stone-III. 16/08/2021 31/08/2021 68%
Towards completion of Mile Stone-III. 01/08/2021 15/08/2021 72%
Towards completion of Mile Stone-III. 16/07/2021 31/07/2021 69%
Towards completion of Mile Stone-III. 16/03/2021 31/03/2021 52%
Towards completion of Mile Stone-III. 01/03/2021 15/03/2021 51%
Towards completion of Mile Stone-III. 16/02/2021 28/02/2021 48%
Towards completion of Mile Stone-II 01/02/2021 15/02/2021 46%
Towards completion of Mile Stone-II 01/01/2021 15/01/2021 42%
Towards completion of Mile Stone-II 16/12/2020 31/12/2020 38%
Towards completion of Mile Stone-II 16/11/2020 30/11/2020 10%
Towards completion of Mile Stone-II 01/11/2020 15/11/2020 33%
Towards completion of Mile Stone-II 01/10/2020 15/10/2020 0%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Competed on 21.10.2021 and inaugurated by Hon'ble PM on 25.10.2021
Project completed on 21.10.2021 and inaugurated by Hon'ble PM on 25.10.2021 15/09/2019 13/03/2021 - 100%
2 Milestone - III
IN PROGRESS 15/09/2019 31/10/2021 - 70%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
101129 Lac. 101129 Lac. 95835 Lac. 95835 Lac. 106423 Lac.