Back     

Project Details

PROJECT NAME :  Construction of 220 KV Electicity sub-station Raja ka Talab
Project Detail / Brief Description:

Construction of 220 KV Substation and related Lines.


Project Department:

U.P. Power Transmission Corporation Limited (UPPTCL)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:

1. Improvement in Voltage , Power Supply in Varanasi and Mirzapur district.
2. Reduction in overloading in Varanasi city.
3. Reduction in chance of electrical instruments due to consistent supply.
4. Better supply of electricity in Varanasi and Mirzapur area.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Ima-Ud-Din Khan eeetd1var@upptcl.org 9415311042 Superintending Engineer
Ramanand eeetd1var@upptcl.org 9415311043 Executive Engineer

 PROJECT DATES
Project Planned Start Date: 03/May/2016 Project Planned Completion Date: 31/May/2018

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Civil Work for Construction of Sub Station
1. Civil Work for Construction of Sub Station 68% completed.
2. Boundary wall 100% completed.
3. Main Gantry Foundation 100% completed.
4. Control room approx 80% completed.
5. Transformer plinth (4 Nos.) completed.
6. Cable Trench approx 85% completed.
7. Earth filling approx 85% completed,
8.Auxiliary Foundation 92 % completed
03/05/2016 28/02/2018 - 70%
2 Supply of Electrical Materials
Supply of Electrical Materials 82% completed. 01/03/2017 28/02/2018 - 80%
3 Erection Work for Construction of Sub Station
Erection Work for Construction of Sub Station up to 70% completed. 15/03/2017 28/02/2018 - 70%
4 Testing and Commissioning of Sub Station
Last activity for energization
- Testing and Commissioning of Sub Station will be start after complete electrical erection work.
30/04/2018 31/05/2018 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
9005 Lac. 0 Lac. 0 Lac. 5639 Lac. 3366 Lac.



Back