Project Details

PROJECT NAME :  Construction of Vrihad Gosanraksh Kendra Bhitkuri Sevapuri
Project Detail / Brief Description:

Construction of Vrihad Gosanraksh Kendra Bhitkuri sevapuri


Project Department:

UP Rajya Nirman Sahkari Sangh Ltd. (PACFED)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Mk shrivastav varanasi1prakhand@gmail.com 7991203644

 PROJECT DATES
Project Planned Start Date: 02/Nov/2019 Project Planned Completion Date: 30/Jun/2020

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Construction of Vrihad Gosanraksh Kendra Bhitkuri Sevapuri
karya purna, Inventory 24-07-2020 ko preshit 02/11/2019 31/07/2020 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
120 Lac. 0 Lac. 120 Lac. 120 Lac. 0 Lac.