PROJECT NAME :  Apartments for Faculty and Officers (S+8) of IIT(BHU)
Project Detail / Brief Description:

The projects consists of construction of two nos. Stilt + 8 floors 3 BHK apartments for the faculty and officers of IIT(BHU), Varanasi.


Project Department:

Central Public Works Department (CPWD)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
ASHOK KUMAR GUPTA eevpd@rediffmail.com 9999798241 Project Head

 PROJECT DATES
Project Planned Start Date: 15/May/2020 Project Planned Completion Date: 14/Dec/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
1. Rcc work will get completed till 31st March, 20 16/03/2021 31/03/2021 60%
RCC slab upto level-10, brick work upto level-8 an 01/02/2021 15/02/2021 30%
Competition of Terrace slabs of Block-2, AAC/Brick 16/01/2021 31/01/2021 0%
Slabs upto level-7 of block-2 and upto level-5 of 16/12/2020 31/12/2020 100%
Slab upto level-7 of block-2 and Slab of level-4 o 01/12/2020 15/12/2020 100%
RCC slabs of Blcok-2 upto level-7 to be completed 16/11/2020 30/11/2020 100%
RCC slabs upto level-6 of blcok-2 and RCC slabs up 01/11/2020 15/11/2020 100%
RCC slabs upto level-5 of Blcok-2 to be completed. 01/10/2020 15/10/2020 100%
1. RCC slab upto level-8 level for block-2 2. R 01/01/2021 15/01/2021 100%
RCC slab upto floor IV level for block-2 completed 16/10/2020 31/10/2020 100%
Stilt floor roof of block no. 2 and beams of stilt 16/10/2020 31/10/2020 100%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 First Milestone
RCC of foundation upto plinth level for block 1 & 2. 15/05/2020 14/08/2020 - 100%
2 First MileStone
RCC of foundation upto plinth level for block 1 & 2. 15/05/2020 14/08/2020 - 100%
3 Second Milestone
For block 1 & 2
1. RCC slab upto Floor level 5
2. Brick work upto floor level 4
3. Sample flat at first floor including submission of soft drawings for flooring works of all building.
B- Activity completion of E&M work:
(a) Slab conduiting upto floor level 6
(b) Wall conduiting upto floor level 4
(c) Sample flat at 1st floor with all wiring, switch, socket, fan fitting etc. installed and complete.
15/08/2020 14/11/2020 - 90%
4 Third Milestone

1. RCC slab upto floor level 9 (terrace level) for block 2 & upto level-7 for block-1
2. Brick work upto floor level 8 for block-2
3. for Block-2 Internal work upto floor level5
4. Water proofing of toilet, internal plumbing, wall filling work upto floor level 4 for block-2 and upto level-2 for block-1
01/02/2021 14/02/2021 - 40%
5 Fourth Milestone
For block 1 & 2
1. Overhead water tank, brick coba complete.
2. Completion of brick work.
3. Complete toilet work including internal plumbing work, wall tiling work.
4. Completion of all flooring work plaster work, brick work etc. in all respect.
15/02/2021 14/05/2021 - 0%
6 Fifth Milestone
For block 1 & 2
1. Completion of external and internal painting, false ceiling of all building and flooring.
2. Completion of external plumbing, sewerage work, drainage and road work.
15/05/2021 14/07/2021 - 0%
7 Sixth Milestone
For block 1 & 2
1. Completion of all works in all respect including testing and commissioning.
15/07/2021 14/08/2021 - 0%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
4001 Lac. 0 Lac. 750 Lac. 891.94156 Lac. 3109.05844 Lac.