Back     

Project Details

PROJECT NAME :  Four Lane Widening of National Highway No.233,PKG-3 (Ghaghra Bridge- Varanasi Division)
Project Detail / Brief Description:

Likely Date of completion - 31.03.2022


Project Department:

National Highways Authority Of India (NHAI)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. S. Yadav var@nhai.org 9984114097 Project Director

 PROJECT DATES
Project Planned Start Date: 01/Jan/2016 Project Planned Completion Date: 30/Apr/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
Towards completion of Project. (Except 15.89 km du 01/05/2022 15/05/2022 97%
Towards completion of Project. (Except 15.89 km du 16/04/2022 30/04/2022 97%
Towards completion of Project. (Except 15.89 km l 16/04/2022 30/04/2022 97%
Towards completion of Project. (Except 15.89 km l 01/04/2022 15/04/2022 97%
Towards completion of Project. 01/03/2022 15/03/2022 95%
Towards completion of Project. 16/10/2020 31/10/2020 94%
Towards completion of Project. 01/10/2020 15/10/2020 94%
Towards completion of Project. 16/10/2020 31/10/2020 94%
Towards completion of Project. 01/10/2020 15/10/2020 94%
Towards completion of Project. 16/09/2021 30/09/2021 94%
Towards completion of Project. 16/08/2021 31/08/2021 90%
Towards Schedule completion. 16/08/2021 31/08/2021 94%
Towards Schedule completion. 01/08/2021 15/08/2021 94%
Towards Schedule completion. 16/07/2021 31/07/2021 93%
Towards Schedule completion. 16/03/2021 31/03/2021 91%
Towards Schedule completion. 01/03/2021 15/03/2021 91%
Towards Schedule completion. 16/02/2021 28/02/2021 90%
Towards Schedule completion. 01/02/2021 15/02/2021 90%
Towards completion of Project. 16/02/2021 03/03/2021 90%
Towards completion of Project. 01/01/2021 15/01/2021 89%
Towards completion of Project. 16/12/2020 31/12/2020 88%
Towards completion of Project. 16/11/2020 30/11/2020 88%
Towards completion of Project. 01/11/2020 15/11/2020 87%
Towards completion of Project. 01/10/2020 15/10/2020 0%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Schedule Completion
Like Date of completed 31.03.2022 01/01/2016 31/03/2022 - 95%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
240528 Lac. 240528 Lac. 211651 Lac. 211651 Lac. 269405 Lac.



Back