Project Details

PROJECT NAME :  Four Lane Widening of NationalHighway No.56, PKG-2 (Sultanpur Varanasi Devision)
Project Detail / Brief Description:

Likely Date of completion - 31.03.2022


Project Department:

National Highways Authority Of India (NHAI)

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
R. S. Yadav var@nhai.org 9984114097 Project Director

 PROJECT DATES
Project Planned Start Date: 01/Jan/2016 Project Planned Completion Date: 31/Jul/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
Towards completion of the Project. The project is 01/05/2022 15/05/2022 89%
Towards completion of the Project. The project is 16/04/2022 30/04/2022 89%
Towards completion of the Project. The project is 16/04/2022 30/04/2022 89%
Towards completion of the Project. The project is 01/04/2022 15/04/2022 89%
Towards Completion of Project, Likely Date of Comp 01/03/2022 15/03/2022 89%
Towards completion of Project. 01/03/2022 15/03/2022 89%
Towards completion of Project. 16/10/2020 31/10/2020 87%
Towards completion of Project. 01/10/2020 15/10/2020 87%
Towards completion of Project. 16/10/2020 31/10/2020 87%
Towards Schedule completion. 01/10/2020 15/10/2020 87%
Towards Schedule completion. 16/09/2021 30/09/2021 87%
Towards Schedule completion (86%). 16/08/2021 31/08/2021 86%
Towards Schedule completion (86%). 16/08/2021 31/08/2021 0%
Towards Schedule completion. 16/07/2021 31/07/2021 86%
Towards Schedule completion. 16/03/2021 31/03/2021 83%
Towards Schedule completion. 01/03/2021 15/03/2021 83%
Towards Schedule completion. 16/02/2021 28/02/2021 82%
Towards Schedule completion. 01/02/2021 15/02/2021 82%
Towards Schedule completion. 01/02/2021 15/02/2021 82%
Towards Schedule completion. 01/01/2021 15/01/2021 81%
Towards Schedule completion. 16/12/2020 31/12/2020 79%
Towards Schedule completion. 16/11/2020 30/11/2020 78%
Towards completion of Project. 01/11/2020 15/11/2020 77%
Towards completion of Project. 01/10/2020 15/10/2020 0%

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Schedule Completion
Likely date of Completion of the Project is 31.03.2022 01/01/2016 31/03/2022 - 89%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
260399 Lac. 260399 Lac. 220929 Lac. 220929 Lac. 299869 Lac.