PROJECT NAME : Laying of Additional Flow Diversion Line From OTS to RTS, Varanasi. |
Project Detail / Brief Description:
Laying of 945 m (1200 mm MS pipe) Sewer line by trench-less technology and Installation of 01 no. Sluice Gate. |
Project Department: Ganga Pollution Prevention Unit, U.P. Jal Nigam |
Associated Yojna Name: AMRUT |
||
Goals, Objectives and Benefits of Project:
Prevention of Sewer over flow at Rajghat Outfall |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
S.K. Burman | ganga@gmail.com | 9450596859 |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 25/Mar/2020 | Project Planned Completion Date: 30/Jan/2022 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Pre-execution activities. | Pre-execution activities such as topographical survey, GPR survey, routes for traffic diversion etc. will be taken up. As the deep sewer line is to be laid by trench-less method, same can not be initiated during monsoon season and most likely to be started from first week of October 2020. | 10/06/2020 | 31/08/2020 | - | 100% |
2 | Supply and laying of MS pipe line by trench-less technology | Work in progress. | 20/10/2020 | 10/11/2021 | - | 65% |
3 | Construction of manholes and installation of Sluice gate | As the pipe line is laid from one pit to another, manholes will be constructed simultaneously. Installation of Sluice gate to control the flow will also be completed by 15.11.2021. | 15/09/2021 | 15/11/2021 | - | 50% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
1062 Lac. | 0 Lac. | 778 Lac. | 656 Lac. | 406 Lac. |