PROJECT NAME :  Laying of Additional Flow Diversion Line From OTS to RTS, Varanasi.
Project Detail / Brief Description:

Laying of 945 m (1200 mm MS pipe) Sewer line by trench-less technology and Installation of 01 no. Sluice Gate.


Project Department:

Ganga Pollution Prevention Unit, U.P. Jal Nigam

Associated Yojna Name:

AMRUT

Goals, Objectives and Benefits of Project:

Prevention of Sewer over flow at Rajghat Outfall
thereby abatement of Pollution of river Ganga.


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
S.K. Burman ganga@gmail.com 9450596859

 PROJECT DATES
Project Planned Start Date: 25/Mar/2020 Project Planned Completion Date: 30/Jan/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Pre-execution activities.
Pre-execution activities such as topographical survey, GPR survey, routes for traffic diversion etc. will be taken up. As the deep sewer line is to be laid by trench-less method, same can not be initiated during monsoon season and most likely to be started from first week of October 2020. 10/06/2020 31/08/2020 - 100%
2 Supply and laying of MS pipe line by trench-less technology
Work in progress. 20/10/2020 10/11/2021 - 65%
3 Construction of manholes and installation of Sluice gate
As the pipe line is laid from one pit to another, manholes will be constructed simultaneously. Installation of Sluice gate to control the flow will also be completed by 15.11.2021. 15/09/2021 15/11/2021 - 50%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
1062 Lac. 0 Lac. 778 Lac. 656 Lac. 406 Lac.