SCHEDULE |
Sr. |
Milestone |
Description |
Start Date |
Planned Completion Date |
Actual Completion Date |
Milestone Completion(In %) |
1 | Kalha Talab
| Dewatering & Cleaning, Earth Work, Pcc, Shuttering, Steel & RCC Work, Finishing Work, Toilet Block, Chattri, Boundary Wall | 10/07/2019 | 09/09/2020 | - | 80% |
2 | Dudhiya Talab
| Dewatering & Cleaning, Earth Work, Pcc, Shuttering, Steel & RCC Work, Finishing Work, Toilet Block, Chattri, Boundary Wall | 10/07/2019 | 09/09/2020 | - | 80% |
3 | Laxmi Talab
| Dewatering & Cleaning, Earth Work, Pcc, Shuttering, Steel & RCC Work, Finishing Work, Toilet Block, Chattri, Boundary Wall | 10/07/2019 | 09/09/2020 | - | 50% |
4 | Bakhariya Talab
| Dewatering & Cleaning, Earth Work, Pcc, Shuttering, Steel & RCC Work, Finishing Work, Toilet Block, Chattri, Boundary Wall | 10/07/2019 | 09/09/2020 | - | 25% |
5 | Avaleshpur Rewa Talab
| Dewatering & Cleaning, Earth Work, Pcc, Shuttering, Steel & RCC Work, Finishing Work, Toilet Block, Chattri, Boundary Wall | 10/07/2019 | 09/09/2020 | - | 5% |
6 | Paharia Talab
| Dewatering & Cleaning, Earth Work, Pcc, Shuttering, Steel & RCC Work, Finishing Work, Toilet Block, Chattri, Boundary Wall | 10/07/2019 | 09/09/2020 | - | 25% |
7 | Karoundhi Panchkoshi Talab
| Dewatering & Cleaning, Earth Work, Pcc, Shuttering, Steel & RCC Work, Finishing Work, Toilet Block, Chattri, Boundary Wall | 10/07/2019 | 09/09/2020 | - | 55% |
8 | Kabir Prakakya Talab
| Dewatering & Cleaning, Earth Work, Pcc, Shuttering, Steel & RCC Work, Finishing Work, Toilet Block, Chattri, Boundary Wall | 10/07/2019 | 09/09/2020 | - | 10% |