PROJECT NAME : PMAY Yojana (Site 2) 608 unit, Harhua |
Project Detail / Brief Description:
Structure work has been completed. Finishing work in Progress. |
Project Department: Varanasi Development Authority (VDA) |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project: |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
Secretary Varanasi | josecy.vsingh@gmail.com | ||
Secretary Varanasi | josecy.vsingh@gmail.com | ||
Secretary Varanasi | josecy.vsingh@gmail.com |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 30/May/2018 | Project Planned Completion Date: 08/Nov/2021 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | Excavation (खुदाई ) | COMPLETED ( ब्लॉक ६ से १ तक ) | 15/05/2019 | 01/08/2019 | - | 100% |
2 | Footing (फोडेशन वर्क ) | COMPLETED (ब्लॉक ६ से १ तक ) | 15/11/2019 | 01/01/2020 | - | 100% |
3 | Up to Plinth (टाई बीम) | COMPLETED | 02/02/2020 | 01/03/2020 | - | 100% |
4 | RCC Frame Work (आरसीसी फ्रेम वर्क) | Block 6 ground to 3rd floor का कार्य पूर्ण हो चूका है | 01/06/2020 | 15/07/2020 | - | 100% |
5 | RCC frame work (आरसीसी फ्रेम वर्क) | Block 5 ground to 3rd floor का कार्य लगभग पूर्ण हो चूका है | 15/07/2020 | 15/09/2020 | - | 90% |
6 | Rcc frame Work (आरसीसी फ्रेम वर्क) | Block ground floor columns and slab का कार्य अभी चल रहा है | 20/08/2020 | 20/12/2020 | - | 15% |
7 | Brick work (चिनाई कार्य ) | Block 6 ground to 3rd floor का कार्य अभी चल रहा है | 15/08/2020 | 15/12/2020 | - | 15% |
8 | Brick work (चिनाई कार्य ) | Block 5 ground to 3rd floor का कार्य अभी चल रहा है | 20/08/2020 | 20/12/2020 | - | 15% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
3832.45 Lac. | 0 Lac. | 1803.1 Lac. | 1803.1 Lac. | 2029.35 Lac. |