PROJECT NAME :  Jham Madai to Narayanpur Kasihar Chukha
Project Detail / Brief Description:

Work is completed


Project Department:

Public Work Department (PWD)

Associated Yojna Name:

PMGSY

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sugreev Ram pdpwdvns@gmail.com 9415391224

 PROJECT DATES
Project Planned Start Date: 01/Feb/2020 Project Planned Completion Date: 31/May/2021

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
1 Earthwork
lenth 7.76 km. out of total lenth 7.76 km. 01/02/2020 31/12/2020 - 100%
2 GSB
lenth 7.760.00 km. out of total 7.760 km. 01/02/2020 31/12/2020 - 100%
3 WBM G-2, G-3
. 01/02/2020 31/01/2021 - 100%
4 PC
Will achieve the target of PC Length 3.50 out of total length 7.760 km by completion of 31-3-2021 15/03/2020 31/03/2021 - 100%

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
339.57 Lac. 0 Lac. 220 Lac. 220 Lac. 119.57 Lac.