PROJECT NAME : Rail Over Bridge at Babatpur - Kapsethi - Bhadohi Road at Railway Crossing No. 21A/2T in Distt. Varanasi |
Project Detail / Brief Description:
Construction of rail over bridge at Babatpur - Kapsethi - road at railway crossing no. 21A/2T |
Project Department: U.P. State Bridge Corporation Ltd. - Varanasi Unit |
Associated Yojna Name: | ||
Goals, Objectives and Benefits of Project:
1. To decongestant Varanasi City in general and vehicles traveling on Babatpur to Bhadohi. |
PROJECT MANAGER / INCHARGE | |||
---|---|---|---|
Name | Contact | Designation | |
suraj kumar garg | bcuvaranasi@gmail.com | 8765973365 | Dy. Project Manager |
PROJECT DATES | ||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Planned Start Date: 01/Mar/2019 | Project Planned Completion Date: 30/Jun/2021 |
15 Days Task | |||
---|---|---|---|
Task Name | Start Date | End Date | Percentage(%) |
कार्य पूर्ण | 01/03/2022 | 15/03/2022 | 0% |
SCHEDULE | ||||||
---|---|---|---|---|---|---|
Sr. | Milestone | Description | Start Date | Planned Completion Date | Actual Completion Date | Milestone Completion(In %) |
1 | फ़ाउंडेशन | कार्य पूर्ण है | 01/03/2019 | 31/08/2020 | - | 100% |
2 | सब स्टृक्चर | कार्य पूर्ण है | 01/07/2019 | 30/11/2020 | - | 100% |
3 | सुपर स्ट्रक्चर | कार्य पूर्ण है | 01/12/2019 | 28/02/2021 | - | 100% |
4 | आर0 ई0 वाल | कार्य पूर्ण है | 01/06/2020 | 31/05/2021 | - | 100% |
5 | सर्विस रोड | कार्य पूर्ण है | 01/03/2021 | 30/06/2021 | - | 100% |
COST & BUDGET | ||||
---|---|---|---|---|
Total Approved Budget (In Lac) A | Total Revised Budget (In Lac)B | Released Budget(In Lac) | Actual Fund consumed till date (In Lac) C | Balance Fund (In Lac) (A+B-C) |
3810.5 Lac. | 0 Lac. | 3810.5 Lac. | 2806.92 Lac. | 1003.58 Lac. |