Back     

Project Details

PROJECT NAME :  Redevelopment of "Namo Ghat"
Project Detail / Brief Description:

Construction work for Phase - I is almost completed and Phase - II is in progress which shall be completed by Dec. 2022.


Project Department:

Smart City Varanasi

Associated Yojna Name:

Goals, Objectives and Benefits of Project:


PROJECT MANAGER / INCHARGE
 Name Email Contact Designation
Sunil Kumar mail@varanasismartcity.gov.in
Rajesh Kumar Trivedi rajesh.trivedi@repl.global 8840994640 Construction Manager, PMC-VSCL
Amrendra Tiwari mail@varanasismartcity.gov.in 9771410338 Senior Engineer

 PROJECT DATES
Project Planned Start Date: 18/Aug/2020 Project Planned Completion Date: 15/May/2022

15 Days Task
 Task Name Start Date End Date Percentage(%)
No Task..

SCHEDULE
Sr. Milestone Description Start Date Planned Completion Date Actual Completion Date Milestone Completion(In %)
No Milestone Assign

COST & BUDGET
Total Approved Budget (In Lac) A Total Revised Budget (In Lac)B Released Budget(In Lac) Actual Fund consumed till date (In Lac) C Balance Fund (In Lac) (A+B-C)
3583 Lac. 0 Lac. 3583 Lac. 1264 Lac. 2319 Lac.



Back